PMI-SP Exam - Topic 1 Question 123 Discussion

Posted by Melda on Oct 12, 2026 at 11:48 AM

You are the project manager of the NHQ project. Your project has a budget of $1,258,456 and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. What is the planned value for this project?

Suggested Answer: A

The planned value is the percent complete that the project should have done. In this instance, it is:

Planned value = 45% of $1,258,456

=$566,305

Answer option B is incorrect. This is the project budget.

Answer option D is incorrect. $503,382 is the earned value for this project.

Answer option C is incorrect. -$54,044 is the variance at completion for your project.


Get Premium PMI-SP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
1 comments · newest first
LA
Laquita 3 days ago
I remember something about planned value being based on the budget and the percentage of completion, but I'm not entirely sure how to calculate it.