You are the project manager of the NHQ project. Your project has a budget of $1,258,456 and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. What is the planned value for this project?
The planned value is the percent complete that the project should have done. In this instance, it is:
Planned value = 45% of $1,258,456
=$566,305
Answer option B is incorrect. This is the project budget.
Answer option D is incorrect. $503,382 is the earned value for this project.
Answer option C is incorrect. -$54,044 is the variance at completion for your project.