A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.
What should the risk manager do in this scenario?
Roy
4 days agoTommy
5 days agoJeannine
6 days agoGraciela
13 days agoMoon
1 months agoJulian
11 days agoArleen
20 days agoDomitila
1 months agoLili
1 months agoEvan
1 months ago