PMI-RMP Exam - Topic 9 Question 53 Discussion
Gary is the project manager for his project. He and the project team have completed the qualitative risk analysis process and are about to enter the quantitative risk analysis process when Mary, the project sponsor, wants to know what quantitative risk analysis will review. Which of the following statements best defines what quantitative risk analysis will review?
C) The quantitative risk analysis process will analyze the effect of risk events that may substantially impact the project's competing demands.
A) The quantitative risk analysis process will review risk events for their probability and impact on the project objectives.
B) The quantitative risk analysis seeks to determine the true cost of each identified risk event and the probability of each risk event to determine the risk exposure.
D) The quantitative risk analysis reviews the results of risk identification and prepares the project for risk response management.
Silvana
10 months agoWinfred
11 months agoWilliam
11 months agoLayla
11 months agoVeda
11 months agoColeen
11 months agoHarris
11 months agoDudley
11 months agoSarah
11 months agoEdmond
12 months agoShay
12 months agoVeronica
12 months ago