New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-RMP Exam - Topic 9 Question 32 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 32
Topic #: 9
[All PMI-RMP Questions]

Mark works as a project manager of the NNH project. In this project, he has created a contingency response that the cost performance index should be less than 0.91. The NHH project has a budget at completion of $950,000 and is 43 percent complete - though the project should be 50 percent complete. The project has spent $470,897 to reach the 43 percent complete milestone. What is the project's cost performance index?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Janey
4 months ago
Totally agree, it's definitely not looking good!
upvoted 0 times
...
Bettina
4 months ago
Wait, how can it be less than 0.91?
upvoted 0 times
...
Casie
4 months ago
I think it's around 0.87.
upvoted 0 times
...
Cecil
4 months ago
The project is behind schedule!
upvoted 0 times
...
Blythe
4 months ago
CPI is calculated as EV/AC.
upvoted 0 times
...
Mary
5 months ago
I think the CPI is calculated by dividing the earned value by the actual cost, but I’m not sure how to find the earned value here.
upvoted 0 times
...
Willodean
5 months ago
I feel like the CPI should be less than 1 since the project is behind schedule, but I’m not confident about the exact calculation.
upvoted 0 times
...
Dottie
5 months ago
This seems similar to a practice question we did on earned value management. I think we need to find the earned value first.
upvoted 0 times
...
Pete
5 months ago
I remember we calculated the cost performance index in class, but I’m not sure if I remember the formula correctly.
upvoted 0 times
...
Hubert
5 months ago
This looks like a tricky question. I'll need to think carefully about the GitOps toolkit and which tool might be built on it.
upvoted 0 times
...
Art
5 months ago
I'm feeling pretty confident about this one. The key is to use the LIKE operator with the '%' wildcard to match all course codes that start with 'M'. Option C is the correct SQL statement.
upvoted 0 times
...
Lanie
5 months ago
Okay, I think I've got this. The key is to use non-default ports for the FMA services to meet the security requirement.
upvoted 0 times
...
Bettina
5 months ago
I think the key here is to engage the learner and get their perspective. Option B seems like the best way to do that.
upvoted 0 times
...
Lemuel
5 months ago
This seems straightforward - the nConstraint Membership Tool lets you add and remove vertices from a dynamic constraint, so C is the correct answer.
upvoted 0 times
...

Save Cancel