PMI-RMP Exam - Topic 9 Question 30 Discussion
Diana is the project manager of the QPS project for her company. In this project Diana and the project team have identified a pure risk. Diana and the project team decided, along with the key stakeholders, to remove the pure risk from the project by changing the project plan altogether. What is a pure risk?
C) It is a risk event that only has a negative side, such as loss of life or limb.
A) It is a risk event that is generated due to errors or omission in the project work.
B) It is a risk event that is created by a risk response.
D) It is a risk event that cannot be avoided because of the order of the work.
Terina
10 months agoDerrick
11 months agoArthur
11 months agoDusti
11 months agoDenny
11 months agoTerrilyn
11 months agoBette
11 months agoNathan
11 months agoMalinda
11 months agoHannah
12 months agoJesusita
12 months agoDahlia
12 months agoRodolfo
12 months ago