PMI-RMP Exam - Topic 9 Question 30 Discussion
Diana is the project manager of the QPS project for her company. In this project Diana and the project team have identified a pure risk. Diana and the project team decided, along with the key stakeholders, to remove the pure risk from the project by changing the project plan altogether. What is a pure risk?
C) It is a risk event that only has a negative side, such as loss of life or limb.
A) It is a risk event that is generated due to errors or omission in the project work.
B) It is a risk event that is created by a risk response.
D) It is a risk event that cannot be avoided because of the order of the work.
Terina
9 months agoDerrick
9 months agoArthur
9 months agoDusti
9 months agoDenny
9 months agoTerrilyn
10 months agoBette
10 months agoNathan
10 months agoMalinda
10 months agoHannah
10 months agoJesusita
10 months agoDahlia
10 months agoRodolfo
10 months ago