PMI-RMP Exam - Topic 9 Question 116 Discussion

Posted by Gladys on May 14, 2026 at 05:34 PM

In the early stages of a manufacturing project, a risk manager has identified a risk with a component provided by an external supplier that might be delayed. The delay may or may not be significant to the project.

What should the risk manager do?

Suggested Answer: C

Setting risk thresholds in collaboration with stakeholders ensures clarity on what is considered tolerable risk. PMBOK Guide and ISO 31000 state:

'Risk thresholds reflect the degree of risk that stakeholders are willing to accept. These should be defined collaboratively at the start of the project.'

--- PMBOK Guide, 6th Edition, Section 11.1

'The organization should define its risk criteria and thresholds, in consultation with stakeholders.'

--- ISO 31000:2018, Section 6.3


PMBOK Guide, 6th Edition, Section 11.1

ISO 31000:2018, Section 6.3

Get Premium PMI-RMP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
27 comments · newest first
JO
Jolene 1 day ago
I think option C is best. Aligning with stakeholders is crucial.
SH
Shad 6 days ago
B is too passive. Medium impact doesn’t address urgency.
NE
Nenita 11 days ago
True, but we need to minimize risks. A backup plan is essential.
KR
Kristel 17 days ago
But what if the new supplier has issues too?
SH
Shad 22 days ago
D seems smart. Engaging another supplier could prevent delays.
NE
Nenita 27 days ago
I lean towards A. Agreeing on a timeline can help manage expectations.
KR
Kristel 1 month ago
I think option C is best. Aligning with stakeholders is crucial.
MA
Margot 1 month ago
True, but better safe than sorry. We need to minimize impact!
DO
Dominga 1 month ago
Engaging another supplier could complicate things. D might backfire.
KE
Kendra 2 months ago
Registering the risk is important too. B is a solid option.
TA
Tabetha 2 months ago
A timeline agreement might not help if they can't deliver.
SU
Sue 2 months ago
Agree, but what if the delay is significant? D could be safer.
MA
Margot 2 months ago
I think aligning with stakeholders is crucial. C seems best.
RO
Rocco 2 months ago
Totally agree, timeline discussions are key!
BE
Bette 2 months ago
Wait, how can we know if the delay is significant?
VE
Veronica 3 months ago
I think registering the risk is a must.
HA
Harris 3 months ago
Engaging another supplier sounds risky too!
GL
Glenn 3 months ago
Definitely should align with stakeholders first.
VA
Vallie 3 months ago
Totally agree, timeline discussions with the supplier are crucial!
LY
Lyndia 3 months ago
Wait, how can we be sure the delay will be significant?
CH
Chara 3 months ago
Registering the risk seems like the safest bet.
PR
Precious 4 months ago
Engaging another supplier could be a smart move!
AG
Agustin 4 months ago
Definitely need to align with stakeholders on the risk threshold.
JU
Juliann 4 months ago
Agreeing on a timeline with the supplier seems like it could help, but what if they still can’t meet it? I’m not confident that’s the best approach.
CO
Corrinne 4 months ago
I’m leaning towards registering the risk with a medium impact, but I wonder if that’s enough without discussing it with the stakeholders first.
CA
Carin 4 months ago
I remember a practice question where we had to assess supplier risks, and I feel like engaging another supplier could be a valid option if the delay is significant.
FE
Felice 6 months ago
I think the risk manager should probably align with stakeholders on the risk threshold, but I'm not entirely sure if that's the best first step.
0/2000 characters

Save Cancel