PMI-RMP Exam - Topic 8 Question 9 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 9
Topic #: 8
[All PMI-RMP Questions]

Harry is the project manager of the MMQ Construction Project. In this project, Harry has identified a supplier who can create stained glass windows for 1,000 window units in the construction project. The supplier is an artist who works by himself, but creates windows for several companies throughout the United States. Management reviews the proposal to use this supplier and while they agree that the supplier is talented, they do not think the artist can fulfill the 1,000 window units in time for the project's deadline. Management asked Harry to find a supplier who can fulfill the completion of the windows by the needed date in the schedule. What risk response has management asked Harry to implement?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Lina
4 months ago
Totally agree, better safe than sorry!
upvoted 0 times
...
Dorthy
4 months ago
Wait, can they really find someone else in time?
upvoted 0 times
...
Sage
4 months ago
I don't think the artist can handle that many windows alone.
upvoted 0 times
...
Kimberely
4 months ago
Definitely a mitigation strategy.
upvoted 0 times
...
Hyun
4 months ago
Sounds like they need a backup plan!
upvoted 0 times
...
Dolores
5 months ago
I remember discussing risk responses in class. If they want to ensure the windows are done on time, it seems like they’re trying to mitigate the risk by finding someone else.
upvoted 0 times
...
Gerardo
5 months ago
I’m a bit confused. Wouldn’t transference be more about shifting the risk to another party? I don’t think that applies here since they just want a different supplier.
upvoted 0 times
...
Delmy
5 months ago
This reminds me of a practice question where we had to choose between avoidance and mitigation. I feel like they want to avoid the risk of late windows by finding a different supplier.
upvoted 0 times
...
Gerald
5 months ago
I think management is looking for a way to reduce the risk of delays, so it might be mitigation? But I'm not entirely sure.
upvoted 0 times
...
Kris
5 months ago
I like the idea of using staff Super Users to provide feedback, but I'm not sure that would be enough on its own. A combination of methods like C seems like the safest bet.
upvoted 0 times
...
Viola
5 months ago
I'm not certain about the specific terms given for the FRA. Did we cover how many would actually be correct? I recall similar questions but they weren't exactly the same.
upvoted 0 times
...
Brande
5 months ago
This seems like a straightforward question. Decentralization does mean less control over data, so I'll go with True.
upvoted 0 times
...
Queen
5 months ago
I've got this one! UAC is all about giving users more control over what software can do on their system. The right answer is definitely B - Limit the privileges of software. Easy peasy.
upvoted 0 times
...
Fannie
5 months ago
No problem, I've done plenty of these types of questions before. I'll just plug the numbers into the formula and round the answer to the nearest whole dollar.
upvoted 0 times
...

Save Cancel