Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 8 Question 81 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 81
Topic #: 8
[All PMI-RMP Questions]

A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.

What should the risk manager do next to find out the correct limit?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Carolann
18 days ago
Wait, did someone say 'rain'? Time to break out the umbrellas, folks! I wonder if the risk manager can do a rain dance to influence the weather.
upvoted 0 times
Augustine
5 days ago
C: Find out the stakeholders' risk appetite
upvoted 0 times
...
Gladis
6 days ago
B: Perform a sensitivity analysis of the risk
upvoted 0 times
...
Marylou
8 days ago
A: Review the agreed-upon risk tolerance
upvoted 0 times
...
...
Sabine
24 days ago
Nah, nah, the answer is clearly using industry standard risk thresholds. Can't go wrong with the tried and true, am I right?
upvoted 0 times
Noelia
13 days ago
A: I think we should review the agreed-upon risk tolerance.
upvoted 0 times
...
...
Gladis
28 days ago
Hold up, I reckon the risk manager should find out the stakeholders' risk appetite. That's the key to understanding what they're really looking for here.
upvoted 0 times
Yong
13 days ago
D: Use industry standard risk thresholds
upvoted 0 times
...
Dannette
16 days ago
C: Find out the stakeholders' risk appetite
upvoted 0 times
...
Felton
20 days ago
B: Perform a sensitivity analysis of the risk
upvoted 0 times
...
Aleta
23 days ago
A: Review the agreed-upon risk tolerance
upvoted 0 times
...
...
Leigha
1 months ago
Well, if you ask me, the risk manager should perform a sensitivity analysis of the risk. That way, they can really get a grip on the situation and make an informed decision.
upvoted 0 times
...
Kenny
1 months ago
But shouldn't the risk manager also consider the stakeholders' risk appetite to make an informed decision?
upvoted 0 times
...
Broderick
1 months ago
Hmm, this is a tricky one. I think the risk manager should review the agreed-upon risk tolerance to find the correct limit. Gotta stick to the plan, you know?
upvoted 0 times
...
Derick
1 months ago
I agree with Dong. It's important to stick to what has been agreed upon.
upvoted 0 times
...
Dong
1 months ago
I think the risk manager should review the agreed-upon risk tolerance.
upvoted 0 times
...
Irene
1 months ago
But what if the stakeholders' risk appetite is different? Maybe we should find that out first.
upvoted 0 times
...
Bobbye
1 months ago
I agree with Merilyn. It's important to stick to the agreed limits.
upvoted 0 times
...
Merilyn
1 months ago
I think the risk manager should review the agreed-upon risk tolerance.
upvoted 0 times
...

Save Cancel