A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.
What should the risk manager do next to find out the correct limit?
Carolann
18 days agoAugustine
5 days agoGladis
6 days agoMarylou
8 days agoSabine
24 days agoNoelia
13 days agoGladis
28 days agoYong
13 days agoDannette
16 days agoFelton
20 days agoAleta
23 days agoLeigha
1 months agoKenny
1 months agoBroderick
1 months agoDerick
1 months agoDong
1 months agoIrene
1 months agoBobbye
1 months agoMerilyn
1 months ago