Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 8 Question 76 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 76
Topic #: 8
[All PMI-RMP Questions]

During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost.

What should the risk manager do to resolve the sponsor and project team members' concerns about risk identification?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

German
11 days ago
Ah, the classic 'I don't see it, so it doesn't exist' approach. The risk manager needs to bring in the big guns (the experts) to show the stakeholders what's really going on. Option D is the way to go, no doubt.
upvoted 0 times
...
Sue
12 days ago
The most knowledgeable members of the team should validate the risk identification processes. That way, the sponsor and team members can't argue with the findings. Option D is the winner here.
upvoted 0 times
...
Lucia
13 days ago
Haha, looks like the sponsor and team members are playing a game of 'Not My Problem.' The risk manager needs to highlight the importance of agreeing on the risk identification to avoid further delays. Option B is the way to go.
upvoted 0 times
...
Lisandra
20 days ago
Wow, the sponsor and project team members are really not on the same page here. The risk manager needs to reinforce that the risk identification was done properly during the last sprint. Option A is the best choice to resolve this issue.
upvoted 0 times
...
Edna
1 months ago
I think the risk manager should conduct a separate meeting to show the risk identification analysis to the stakeholders. That way they can see the data and understand the potential impact on the project cost. Option C is the way to go.
upvoted 0 times
Florinda
6 days ago
C) Conduct a separate meeting to show the risk identification analysis to the stakeholders.
upvoted 0 times
...
Ardella
15 days ago
A) Reinforce to the stakeholders that the risk identification was done properly during the last sprint.
upvoted 0 times
...
...
Curtis
1 months ago
Maybe conducting a separate meeting to discuss the analysis could help address concerns.
upvoted 0 times
...
Kris
1 months ago
I agree with Mitsue. It's important to show that the process was followed correctly.
upvoted 0 times
...
Mitsue
2 months ago
I think the risk manager should reinforce that the risk identification was done properly.
upvoted 0 times
...
Pedro
2 months ago
I believe conducting a separate meeting to discuss the risk identification analysis could also help address concerns.
upvoted 0 times
...
Javier
2 months ago
I agree with Maurine. It's important to show that the process was thorough.
upvoted 0 times
...
Maurine
2 months ago
I think the risk manager should reinforce that the risk identification was done properly.
upvoted 0 times
...

Save Cancel