PMI-RMP Exam - Topic 8 Question 76 Discussion
During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost.What should the risk manager do to resolve the sponsor and project team members' concerns about risk identification?
C) Conduct a separate meeting to show the risk identification analysis to the stakeholders.
A) Reinforce to the stakeholders that the risk identification was done properly during the last sprint.
B) Highlight the importance of agreeing on the risk identification to avoid further delays.
D) Ensure that the most knowledgeable members of the team validate risk identification processes.
Beatriz
10 months agoHolley
10 months agoQueenie
10 months agoKeshia
10 months agoDaniela
11 months agoAngella
11 months agoCasie
11 months agoGilberto
11 months agoMaryrose
11 months agoRima
11 months agoSharika
11 months agoTawanna
11 months agoCeleste
11 months agoOdelia
12 months agoMy
12 months agoCarma
12 months agoGerman
1 year agoSue
1 year agoLucia
1 year agoAileen
1 year agoAngella
1 year agoAntonio
1 year agoLisandra
1 year agoJanet
1 year agoLennie
1 year agoBarrett
1 year agoEdna
1 year agoFlorinda
1 year agoArdella
1 year agoCurtis
1 year agoKris
1 year agoMitsue
1 year agoPedro
1 year agoJavier
1 year agoMaurine
1 year ago