PMI-RMP Exam - Topic 8 Question 76 Discussion
During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost.What should the risk manager do to resolve the sponsor and project team members' concerns about risk identification?
C) Conduct a separate meeting to show the risk identification analysis to the stakeholders.
A) Reinforce to the stakeholders that the risk identification was done properly during the last sprint.
B) Highlight the importance of agreeing on the risk identification to avoid further delays.
D) Ensure that the most knowledgeable members of the team validate risk identification processes.
Beatriz
8 months agoHolley
8 months agoQueenie
8 months agoKeshia
9 months agoDaniela
9 months agoAngella
9 months agoCasie
9 months agoGilberto
9 months agoMaryrose
10 months agoRima
10 months agoSharika
10 months agoTawanna
10 months agoCeleste
10 months agoOdelia
10 months agoMy
10 months agoCarma
10 months agoGerman
1 year agoSue
1 year agoLucia
1 year agoAileen
1 year agoAngella
1 year agoAntonio
1 year agoLisandra
1 year agoJanet
1 year agoLennie
1 year agoBarrett
1 year agoEdna
1 year agoFlorinda
1 year agoArdella
1 year agoCurtis
1 year agoKris
1 year agoMitsue
1 year agoPedro
1 year agoJavier
1 year agoMaurine
1 year ago