Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-RMP Exam - Topic 8 Question 108 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 108
Topic #: 8
[All PMI-RMP Questions]

An experienced and the only developer on a software implementation project will be on leave for several weeks. The risk of this critical resource's availability was added to the risk register. Contingencies were made for a support developer to job shadow this resource, depending on how things go prior to their leave. The project team was pleased with the backup plan and the new resource was able to shadow for a few weeks.

What should the risk manager do next?

Show Suggested Answer Hide Answer
Suggested Answer: B

Once the contingency plan has been executed (e.g., the backup resource has shadowed the experienced developer), it is crucial to continuously monitor and manage any residual or secondary risks that may arise. These risks could include the backup resource's ability to perform effectively or the potential impact of the original developer's absence on project timelines. By updating the risk register and maintaining communication with the project team, the risk manager ensures that the project remains on track and that any new risks are promptly addressed, in alignment with PMI's best practices for ongoing risk management.


Contribute your Thoughts:

0/2000 characters
Edelmira
5 days ago
Option D could work, but it feels like a temporary fix.
upvoted 0 times
...
Coral
10 days ago
I like option C. A permanent developer would provide long-term stability.
upvoted 0 times
...
Shanice
15 days ago
Option A seems too quick. We shouldn't close the risk just yet.
upvoted 0 times
...
Cortney
21 days ago
Agreed! We need to keep an eye on the backup resource's performance.
upvoted 0 times
...
Elmira
26 days ago
I think option B is the best. Continuous monitoring is key.
upvoted 0 times
...
Nana
1 month ago
I agree with B, but I wonder if the backup will really be effective.
upvoted 0 times
...
Mitsue
1 month ago
D could lead to more confusion later on.
upvoted 0 times
...
Annamae
2 months ago
Surprised they didn't hire someone permanent right away!
upvoted 0 times
...
Gladys
2 months ago
A seems too quick. The risk isn't fully resolved yet.
upvoted 0 times
...
Kris
2 months ago
I think B is the best option. Continuous monitoring is key!
upvoted 0 times
...
Clarinda
2 months ago
Haha, the experienced dev better not take a vacation to the Bahamas!
upvoted 0 times
...
Cassie
3 months ago
B is the way to go. Gotta keep an eye on those residual risks.
upvoted 0 times
...
Dick
3 months ago
D is a good option too. Hiring another developer as a contingency plan is smart.
upvoted 0 times
...
Lisandra
3 months ago
B is the correct answer. Continuously monitoring the backup resource is crucial.
upvoted 0 times
...
Vanesa
3 months ago
I’m not confident about this, but I think option D might be too reactive. Shouldn't we focus on the backup resource first before hiring someone else?
upvoted 0 times
...
Ettie
3 months ago
I’m leaning towards option C because hiring a permanent developer could provide long-term stability, but I wonder if that’s overkill for just a few weeks.
upvoted 0 times
...
Gianna
3 months ago
I think we practiced a similar question where we had to decide on risk management strategies. I feel like updating the risk register is important, but I’m torn between A and B.
upvoted 0 times
...
Carmelina
4 months ago
I'm a little unsure on this one. Do we really need to hire another permanent developer? That seems like overkill if the experienced developer is just going to be out for a few weeks. I'm torn between options B and D.
upvoted 0 times
...
Kristofer
4 months ago
I feel pretty confident about this one. The risk has already occurred, so I think the best approach is to update the risk register and closely monitor the backup resource to address any secondary risks that come up.
upvoted 0 times
...
Willow
4 months ago
I remember we discussed the importance of monitoring residual risks, so option B seems like a good choice, but I'm not entirely sure if we should close the risk just yet.
upvoted 0 times
...
Patti
5 months ago
I’m leaning towards B too. Communication is crucial for project success.
upvoted 0 times
...
Eun
5 months ago
Okay, let's think this through step-by-step. The risk has already materialized, so we need to update the register. Then, we should continuously monitor the backup resource and communicate any residual or secondary risks. Hiring another permanent developer doesn't seem necessary based on the information provided.
upvoted 0 times
...
Helga
5 months ago
Okay, let's see here. The key seems to be managing the risk and ensuring the project is covered during the experienced developer's absence. I'm leaning towards option B, but I'll need to think it through a bit more.
upvoted 0 times
...
Brittney
5 months ago
Hmm, this seems like a tricky one. I'll need to carefully consider the options and think through the potential implications of each approach.
upvoted 0 times
But what if the backup resource isn't up to speed?
upvoted 0 times
...
Shad
4 months ago
Agreed! We can't just assume everything will be fine.
upvoted 0 times
...
Pearline
4 months ago
I think option B is the best. Continuous monitoring is key.
upvoted 0 times
...
...

Save Cancel