PMI-RMP Exam - Topic 7 Question 98 Discussion
An organization is executing two projects---Project A and Project B---simultaneously A previously identified risk will impact the schedule for Project
B) Consult with Project B's risk manager and determine where synergies might exist between the risk management plans for both projects.
A) While executing the mitigation plan a number of residual risks are identified that could provide cost savings for Project B.
Which action should the risk manager for Project A take?
A) Continue executing the planned risk mitigation to avoid any additional schedule impact to Project A.
C) Review the findings in Project A's closure documents and propose a new organizational process for portfolio risk management.
D) Combine the risk registers for Project A and Project B and determine if there are any additional cross-project opportunities to exploit.
Leonora
5 months agoAlita
6 months agoArlette
6 months agoMerilyn
6 months agoSantos
6 months agoDaniel
7 months agoMerilyn
7 months agoRebeca
7 months agoRossana
7 months agoErick
7 months agoArthur
8 months agoNana
8 months agoRodney
8 months agoGwenn
8 months ago