Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-RMP Exam - Topic 7 Question 98 Discussion

Posted by Wilda on Mar 03, 2025 at 10:26 PM

An organization is executing two projects---Project A and Project B---simultaneously A previously identified risk will impact the schedule for Project

Suggested Answer: B

Get Premium PMI-RMP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
14 comments · newest first
LE
Leonora 10 months ago
Not sure if combining risks is a good idea, could complicate things.
AL
Alita 11 months ago
Wait, combining risk registers? Isn't that risky?
AR
Arlette 11 months ago
I think we should stick with A to avoid more delays.
ME
Merilyn 11 months ago
Option B seems smart, collaboration is key!
SA
Santos 11 months ago
Totally agree with B, synergies can save us time and money!
DA
Daniel 11 months ago
I vaguely recall something about reviewing closure documents being important, but I don't know if that applies here. Option C seems a bit off to me.
ME
Merilyn 12 months ago
I feel like we discussed the importance of sticking to the mitigation plan in class, so maybe option A is the safest bet?
RE
Rebeca 12 months ago
I remember a practice question where we had to choose between focusing on one project or looking for synergies. I think option D might be a good choice too.
RO
Rossana 1 year ago
I'm not entirely sure, but I think option B makes sense since collaborating could help both projects.
ER
Erick 1 year ago
I think the answer is to consult with the Project B risk manager and see if there are any synergies between the risk management plans. That way, we can potentially find some cost savings while still protecting the schedule for Project A.
AR
Arthur 1 year ago
I'm a bit confused here. Should I be looking for cost savings for Project B or sticking to the original risk mitigation plan for Project A? I'll need to read through the question again carefully.
NA
Nana 1 year ago
Okay, I've got this. The best approach is to continue executing the planned risk mitigation for Project A to avoid any further schedule impact. Then, I'll review the findings and propose a new organizational process for portfolio risk management.
RO
Rodney 1 year ago
Hmm, this seems like a classic case of having to balance the needs of two different projects. I think the key is to consult with the other project manager and see if there are any opportunities to leverage the risk mitigation efforts.
GW
Gwenn 1 year ago
This is a tricky one. I'm not sure if I should focus on mitigating the risk for Project A or try to find synergies with Project B. I'll need to carefully weigh the options.
0/2000 characters

Save Cancel