PMI-RMP Exam - Topic 7 Question 85 Discussion
A risk manager recently had to take an unexpected leave of absence. An interim risk manager has been tasked with completing risk planning for a new project. The interim risk manager has been provided with a strength, weaknesses, opportunities, and threats (SWOT) analysis that was completed during a project kickoff meeting several weeks ago.What should the interim risk manager do to derive actionable risk responses from the SWOT analysis?
A) Determine risks from the SWOT analysis and break them down into threats and opportunities.
B) Work with the project sponsor to understand which items they would prioritize from the SWOT analysis.
C) Conduct an extensive review with the project team to ensure all SWOT items can be mitigated or eliminated.
D) Input the items identified on the SWOT analysis into the project's risk register for consideration as-is.
Nan
10 months agoWhitley
10 months agoJunita
10 months agoHelaine
10 months agoRoslyn
11 months agoMickie
11 months agoYolande
11 months agoSabra
11 months agoRebbecca
11 months agoTawna
11 months agoIlene
11 months agoMartha
11 months agoRicki
11 months agoFranklyn
12 months agoRosalyn
1 year agoLeonora
1 year agoRoslyn
1 year agoJoanne
1 year agoEileen
1 year agoGabriele
1 year agoBritt
1 year agoShawnda
1 year agoRima
1 year agoTrina
1 year agoHannah
1 year agoMelynda
1 year agoAhmad
1 year agoAlba
1 year agoCorinne
1 year agoArlean
1 year agoHelaine
1 year agoDanica
1 year agoHubert
1 year agoIvette
1 year agoMatilda
1 year ago