PMI-RMP Exam - Topic 7 Question 85 Discussion
A risk manager recently had to take an unexpected leave of absence. An interim risk manager has been tasked with completing risk planning for a new project. The interim risk manager has been provided with a strength, weaknesses, opportunities, and threats (SWOT) analysis that was completed during a project kickoff meeting several weeks ago.What should the interim risk manager do to derive actionable risk responses from the SWOT analysis?
A) Determine risks from the SWOT analysis and break them down into threats and opportunities.
B) Work with the project sponsor to understand which items they would prioritize from the SWOT analysis.
C) Conduct an extensive review with the project team to ensure all SWOT items can be mitigated or eliminated.
D) Input the items identified on the SWOT analysis into the project's risk register for consideration as-is.
Nan
6 months agoWhitley
6 months agoJunita
7 months agoHelaine
7 months agoRoslyn
7 months agoMickie
7 months agoYolande
8 months agoSabra
8 months agoRebbecca
8 months agoTawna
8 months agoIlene
8 months agoMartha
8 months agoRicki
8 months agoFranklyn
8 months agoRosalyn
1 year agoLeonora
11 months agoRoslyn
11 months agoJoanne
11 months agoEileen
12 months agoGabriele
1 year agoBritt
1 year agoShawnda
1 year agoRima
12 months agoTrina
1 year agoHannah
1 year agoMelynda
1 year agoAhmad
1 year agoAlba
1 year agoCorinne
1 year agoArlean
1 year agoHelaine
1 year agoDanica
1 year agoHubert
1 year agoIvette
1 year agoMatilda
1 year ago