Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 7 Question 85 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 85
Topic #: 7
[All PMI-RMP Questions]

A risk manager recently had to take an unexpected leave of absence. An interim risk manager has been tasked with completing risk planning for a new project. The interim risk manager has been provided with a strength, weaknesses, opportunities, and threats (SWOT) analysis that was completed during a project kickoff meeting several weeks ago.

What should the interim risk manager do to derive actionable risk responses from the SWOT analysis?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Rosalyn
4 days ago
I'm surprised option B is even an option. Relying on the project sponsor to prioritize the SWOT? That's like asking a toddler to fix your car - it's just not going to end well.
upvoted 0 times
...
Gabriele
8 days ago
Option A is the way to go. Splitting the SWOT into threats and opportunities is the first step in turning that analysis into actionable responses. It's like separating the wheat from the chaff, you know?
upvoted 0 times
...
Britt
9 days ago
I'm all for option C - an extensive review with the team is crucial. We can't just take the SWOT at face value, we need to understand it inside and out to mitigate those risks.
upvoted 0 times
...
Shawnda
11 days ago
Option D is just lazy. Throwing the SWOT analysis into the risk register without any analysis? That's like trying to solve a Rubik's Cube by shaking it really hard.
upvoted 0 times
...
Melynda
1 months ago
The SWOT analysis is a great starting point, but the interim manager needs to dig deeper to derive actionable risk responses. I think option B is the way to go - collaborating with the project sponsor to prioritize the SWOT items is key.
upvoted 0 times
Alba
1 days ago
A) That sounds like a good approach. Prioritizing with the sponsor will help focus on the most critical risks.
upvoted 0 times
...
Corinne
6 days ago
B) I agree, working with the project sponsor to prioritize the SWOT items will help focus on the most critical risks.
upvoted 0 times
...
Arlean
8 days ago
A) Determine risks from the SWOT analysis and break them down into threats and opportunities.
upvoted 0 times
...
Helaine
22 days ago
B) Work with the project sponsor to understand which items they would prioritize from the SWOT analysis.
upvoted 0 times
...
Danica
24 days ago
A) Determine risks from the SWOT analysis and break them down into threats and opportunities.
upvoted 0 times
...
...
Hubert
1 months ago
I believe working with the project sponsor to understand their priorities (Option B) is also crucial in this situation.
upvoted 0 times
...
Ivette
2 months ago
I agree with Matilda. It's important to prioritize and categorize the risks to develop effective responses.
upvoted 0 times
...
Matilda
2 months ago
I think the interim risk manager should determine risks from the SWOT analysis and break them down into threats and opportunities (Option A).
upvoted 0 times
...

Save Cancel