PMI-RMP Exam - Topic 7 Question 83 Discussion
After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.How could the risk manager have avoided the board's response?
A) Engaging the key stakeholders during the prioritization process
B) Prioritizing the risks based on the project sponsor's risk appetite
C) Engaging with the project sponsor before presenting to the board
D) Working with an established industry standard prioritization method
Candida
10 months agoMyrtie
10 months agoEladia
10 months agoRebbeca
10 months agoEvangelina
11 months agoClarinda
11 months agoBeckie
11 months agoRyan
11 months agoPamella
11 months agoKristel
11 months agoShantay
11 months agoAntione
11 months agoYasuko
11 months agoEdwin
12 months agoAmalia
12 months agoMarkus
1 year agoErick
1 year agoJamika
1 year agoYolando
1 year agoGeorgeanna
1 year agoViola
1 year agoArlette
1 year agoJustine
1 year agoIrving
1 year agoJules
1 year agoClare
1 year agoErin
1 year agoLonna
1 year agoLelia
1 year ago