After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.
How could the risk manager have avoided the board's response?
Markus
1 months agoErick
18 days agoJamika
23 days agoYolando
1 months agoGeorgeanna
1 months agoViola
1 months agoArlette
16 days agoJustine
19 days agoIrving
23 days agoJules
26 days agoClare
1 months agoErin
2 months agoLonna
2 months agoLelia
2 months ago