PMI-RMP Exam - Topic 7 Question 83 Discussion
After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.How could the risk manager have avoided the board's response?
A) Engaging the key stakeholders during the prioritization process
B) Prioritizing the risks based on the project sponsor's risk appetite
C) Engaging with the project sponsor before presenting to the board
D) Working with an established industry standard prioritization method
Candida
8 months agoMyrtie
8 months agoEladia
8 months agoRebbeca
9 months agoEvangelina
9 months agoClarinda
9 months agoBeckie
9 months agoRyan
9 months agoPamella
10 months agoKristel
10 months agoShantay
10 months agoAntione
10 months agoYasuko
10 months agoEdwin
10 months agoAmalia
10 months agoMarkus
1 year agoErick
1 year agoJamika
1 year agoYolando
1 year agoGeorgeanna
1 year agoViola
1 year agoArlette
1 year agoJustine
1 year agoIrving
1 year agoJules
1 year agoClare
1 year agoErin
1 year agoLonna
1 year agoLelia
1 year ago