A project team has completed the risk response plan for a newly identified major project risk. Some team members argue the plan does not totally eliminate the risk, considering the effort required to implement it, and feel the planned response should be thrown out altogether.
What should the risk manager do in this situation?
In risk management, it is common that not all risks can be completely eliminated. Residual risk is the remaining risk after all possible mitigation efforts have been applied. If the residual risk is within the organization's risk appetite---meaning the organization is willing to accept this level of risk---it is appropriate to proceed with the plan. The PMI framework supports this approach, as risk management is about balancing effort and benefit, ensuring that mitigation efforts are commensurate with the risk involved.
Ligia
13 hours agoSharan
6 days agoNina
11 days agoElena
16 days agoCherry
21 days agoKayleigh
26 days agoArmando
1 month agoLeigha
1 month agoLinwood
1 month agoRuthann
2 months agoLauran
2 months agoTaryn
2 months agoEdna
2 months agoMarvel
2 months agoAnisha
2 months agoColette
3 months agoBritt
3 months agoCarmelina
3 months agoMattie
3 months ago