The project risk manager for an environmental preservation project has started the process of monitoring and controlling risks, The project manager has asked the project team to document the results of this process.How should this documentation be utilized in the future?
B) To ensure information is recorded for lessons learned
A) To return the remaining amount of the contingency reserve
C) To comply with the rules and regulations
D) To hold those who created the risk accountable

PMI-RMP Exam - Topic 6 Question 122 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 122
Topic #: 6
[All PMI-RMP Questions]

The project risk manager for an environmental preservation project has started the process of monitoring and controlling risks, The project manager has asked the project team to document the results of this process.

How should this documentation be utilized in the future?

Show Suggested Answer Hide Answer
Suggested Answer: B

Documenting the results of the risk monitoring and controlling process is important for creating lessons learned. This helps future projects by providing a reference for risk management practices and experiences.

The documentation of the results of monitoring and controlling risks is a valuable source of information for lessons learned. Lessons learned are the documented information that reflects both the positive and negative experiences of a project. They represent the organization's commitment to project management excellence and the project manager's opportunity to learn from the actual experiences of others. By documenting the results of monitoring and controlling risks, the project team can capture the effectiveness of the risk responses, the changes in the risk exposure, the root causes of the risks, the best practices and the lessons learned for future projects.This documentation can help to improve the risk management process, enhance the project performance, and increase the organizational knowledge base.Reference: PMI Risk Management Professional (PMI-RMP) Examination Content Outline and Specifications1, page 10; A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 406;Lessons learned - PMI.


Contribute your Thoughts:

0/2000 characters
Holley
11 hours ago
I remember a practice question about risk management where we discussed compliance, but I feel like that’s not the main focus here.
upvoted 0 times
...
Osvaldo
6 days ago
I think the documentation should definitely be used for lessons learned, but I'm not entirely sure if that's the only purpose.
upvoted 0 times
...

Save Cancel