Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 6 Question 103 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 103
Topic #: 6
[All PMI-RMP Questions]

During project execution for a software development program, a risk manager notices the results vary from the stated expectations in the planning phase. The project team states that there was unrealistic planning.

What should the risk manager do next to understand the differences between planning and execution?

Show Suggested Answer Hide Answer
Suggested Answer: D

Assumptions made during planning need to be reviewed to understand deviations in actual results. PMBOK Guide states:

'Reviewing project assumptions is key to understanding variances between planned and actual performance, as invalid or changed assumptions often cause project deviations.'

--- PMBOK Guide, 6th Edition, Section 11.2


PMBOK Guide, 6th Edition, Section 11.2

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel