A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.
What should the risk manager advise the project manager?
Elden
5 months agoJackie
5 months agoCharlene
5 months agoDiego
5 months agoOretha
6 months agoWillis
6 months agoSusana
6 months agoKara
6 months agoLatricia
6 months agoGlenn
6 months agoGilberto
6 months agoCarissa
6 months agoFletcher
7 months agoRuthann
11 months agoVince
10 months agoGarry
10 months agoJessenia
10 months agoMona
10 months agoMonte
11 months agoKeneth
10 months agoPaulina
10 months agoAlfred
11 months agoEllsworth
11 months agoVal
10 months agoAntonio
10 months agoCarylon
10 months agoJaime
12 months agoPatti
11 months agoBilly
11 months agoErnest
11 months agoAshleigh
1 year agoBritt
10 months agoWillis
11 months agoNenita
11 months agoCarin
12 months agoReiko
12 months agoRusty
1 year agoWendell
1 year agoKallie
1 year ago