A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.
What should the risk manager advise the project manager?
Elden
10 months agoJackie
10 months agoCharlene
10 months agoDiego
10 months agoOretha
11 months agoWillis
11 months agoSusana
11 months agoKara
11 months agoLatricia
11 months agoGlenn
11 months agoGilberto
11 months agoCarissa
11 months agoFletcher
11 months agoRuthann
1 year agoVince
1 year agoGarry
1 year agoJessenia
1 year agoMona
1 year agoMonte
1 year agoKeneth
1 year agoPaulina
1 year agoAlfred
1 year agoEllsworth
1 year agoVal
1 year agoAntonio
1 year agoCarylon
1 year agoJaime
1 year agoPatti
1 year agoBilly
1 year agoErnest
1 year agoAshleigh
1 year agoBritt
1 year agoWillis
1 year agoNenita
1 year agoCarin
1 year agoReiko
1 year agoRusty
1 year agoWendell
1 year agoKallie
1 year ago