A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.
What should the risk manager advise the project manager?
Ruthann
2 days agoMonte
6 days agoEllsworth
13 days agoJaime
25 days agoAshleigh
1 months agoNenita
3 days agoCarin
15 days agoReiko
19 days agoRusty
1 months agoWendell
2 months agoKallie
2 months ago