New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-RMP Exam - Topic 4 Question 91 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 91
Topic #: 4
[All PMI-RMP Questions]

A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.

What should the risk manager advise the project manager?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Elden
3 months ago
Just a reminder, secondary risks are part of the game in project management.
upvoted 0 times
...
Jackie
3 months ago
Totally agree, updating the risk plan is crucial!
upvoted 0 times
...
Charlene
3 months ago
Wait, how can new risks just pop up like that?
upvoted 0 times
...
Diego
4 months ago
I think addressing the secondary risks is the way to go.
upvoted 0 times
...
Oretha
4 months ago
Sounds like a classic case of risk management in action!
upvoted 0 times
...
Willis
4 months ago
I recall a practice question where we had to apply a risk acceptance strategy, but I don't think that's the best option here since there are new risks involved.
upvoted 0 times
...
Susana
4 months ago
I feel like escalating the new risks to stakeholders might be a bit too much unless they directly affect the project timeline.
upvoted 0 times
...
Kara
4 months ago
I'm not entirely sure, but I think updating the risk management plan with new probabilities and impacts could be important. It feels like a proactive approach.
upvoted 0 times
...
Latricia
5 months ago
I remember we discussed how secondary risks can emerge from primary risks, so I think addressing them as per the risk management plan makes sense.
upvoted 0 times
...
Glenn
5 months ago
Ah, this is a good one. I'd recommend updating the risk management plan to reflect the changed probabilities and impacts, then adjusting the response accordingly.
upvoted 0 times
...
Gilberto
5 months ago
Okay, I think I've got a good handle on this. The key is to address the new risks as per the existing risk management plan. That seems like the most straightforward approach.
upvoted 0 times
...
Carissa
5 months ago
Hmm, I'm a bit unsure here. I'll need to think through the options and make sure I understand the implications of each approach.
upvoted 0 times
...
Fletcher
5 months ago
This seems like a tricky situation. I'll need to carefully review the risk management plan and consider the potential impact of the new risks.
upvoted 0 times
...
Ruthann
9 months ago
I bet the risk manager is wishing they had a risk management plan that could handle the unexpected. Maybe they should have consulted a magic 8-ball instead.
upvoted 0 times
Vince
8 months ago
It's important for the project manager and risk manager to communicate effectively and collaborate on finding solutions to address the new risks.
upvoted 0 times
...
Garry
8 months ago
The project manager could consider reallocating resources or seeking additional support to mitigate the impact of the unexpected risks.
upvoted 0 times
...
Jessenia
8 months ago
Maybe the risk manager can suggest adjusting the project schedule to account for the potential delays caused by the new risks.
upvoted 0 times
...
Mona
9 months ago
The risk manager should advise the project manager to review the transition plan and assess the impact of the new risks.
upvoted 0 times
...
...
Monte
9 months ago
A is a cop-out. You can't just accept new risks without a proper plan. The risk manager needs to be proactive and address these issues.
upvoted 0 times
Keneth
8 months ago
Let's communicate with the project team and stakeholders about the potential delays and work together to find solutions.
upvoted 0 times
...
Paulina
9 months ago
We should update the risk register and develop mitigation strategies for the new risks that have emerged.
upvoted 0 times
...
Alfred
9 months ago
We need to reassess the impact of transitioning the responsibilities to the new resource.
upvoted 0 times
...
...
Ellsworth
10 months ago
D is the way to go. Escalating the new risks to the stakeholders is crucial to ensure proper communication and buy-in for the risk management process.
upvoted 0 times
Val
8 months ago
D) Escalate the new risks immediately to the project stakeholders to ensure proper risk communication is in place.
upvoted 0 times
...
Antonio
8 months ago
B) Address these secondary risks as per the risk management plan
upvoted 0 times
...
Carylon
9 months ago
A) Apply a risk acceptance strategy to the new risks as there is no risk response plan.
upvoted 0 times
...
...
Jaime
10 months ago
I think C is the best option. The risk manager should update the plan to reflect the new probabilities and impacts, and then adjust the response accordingly.
upvoted 0 times
Patti
9 months ago
C) Update the risk management plan with the new probability/impact and change the response.
upvoted 0 times
...
Billy
9 months ago
B) Address these secondary risks as per the risk management plan
upvoted 0 times
...
Ernest
9 months ago
A) Apply a risk acceptance strategy to the new risks as there is no risk response plan.
upvoted 0 times
...
...
Ashleigh
10 months ago
Option B seems like the most logical choice. The risk management plan should already have provisions for addressing any secondary risks that arise from the initial risk response.
upvoted 0 times
Britt
8 months ago
D) Escalate the new risks immediately to the project stakeholders to ensure proper risk communication is in place.
upvoted 0 times
...
Willis
9 months ago
C) Update the risk management plan with the new probability/impact and change the response.
upvoted 0 times
...
Nenita
9 months ago
C) Update the risk management plan with the new probability/impact and change the response.
upvoted 0 times
...
Carin
10 months ago
B) Address these secondary risks as per the risk management plan
upvoted 0 times
...
Reiko
10 months ago
B) Address these secondary risks as per the risk management plan
upvoted 0 times
...
...
Rusty
11 months ago
I believe the risk manager should also update the risk management plan with the new probability/impact and change the response accordingly.
upvoted 0 times
...
Wendell
11 months ago
I agree with Kallie. It's important to follow the risk management plan to mitigate any potential negative impacts on the project.
upvoted 0 times
...
Kallie
11 months ago
I think the risk manager should advise the project manager to address these secondary risks as per the risk management plan.
upvoted 0 times
...

Save Cancel