A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.
What should the risk manager advise the project manager?
Elden
8 months agoJackie
8 months agoCharlene
8 months agoDiego
9 months agoOretha
9 months agoWillis
9 months agoSusana
9 months agoKara
9 months agoLatricia
10 months agoGlenn
10 months agoGilberto
10 months agoCarissa
10 months agoFletcher
10 months agoRuthann
1 year agoVince
1 year agoGarry
1 year agoJessenia
1 year agoMona
1 year agoMonte
1 year agoKeneth
1 year agoPaulina
1 year agoAlfred
1 year agoEllsworth
1 year agoVal
1 year agoAntonio
1 year agoCarylon
1 year agoJaime
1 year agoPatti
1 year agoBilly
1 year agoErnest
1 year agoAshleigh
1 year agoBritt
1 year agoWillis
1 year agoNenita
1 year agoCarin
1 year agoReiko
1 year agoRusty
1 year agoWendell
1 year agoKallie
1 year ago