A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.
What should the risk manager advise the project manager?
Elden
3 months agoJackie
3 months agoCharlene
3 months agoDiego
4 months agoOretha
4 months agoWillis
4 months agoSusana
4 months agoKara
4 months agoLatricia
5 months agoGlenn
5 months agoGilberto
5 months agoCarissa
5 months agoFletcher
5 months agoRuthann
9 months agoVince
8 months agoGarry
8 months agoJessenia
8 months agoMona
9 months agoMonte
9 months agoKeneth
8 months agoPaulina
9 months agoAlfred
9 months agoEllsworth
10 months agoVal
8 months agoAntonio
8 months agoCarylon
9 months agoJaime
10 months agoPatti
9 months agoBilly
9 months agoErnest
9 months agoAshleigh
10 months agoBritt
8 months agoWillis
9 months agoNenita
9 months agoCarin
10 months agoReiko
10 months agoRusty
11 months agoWendell
11 months agoKallie
11 months ago