A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.
What should the risk manager advise the project manager?
Elden
6 months agoJackie
6 months agoCharlene
7 months agoDiego
7 months agoOretha
7 months agoWillis
7 months agoSusana
8 months agoKara
8 months agoLatricia
8 months agoGlenn
8 months agoGilberto
8 months agoCarissa
8 months agoFletcher
8 months agoRuthann
1 year agoVince
11 months agoGarry
11 months agoJessenia
12 months agoMona
12 months agoMonte
1 year agoKeneth
12 months agoPaulina
12 months agoAlfred
1 year agoEllsworth
1 year agoVal
12 months agoAntonio
12 months agoCarylon
12 months agoJaime
1 year agoPatti
1 year agoBilly
1 year agoErnest
1 year agoAshleigh
1 year agoBritt
12 months agoWillis
1 year agoNenita
1 year agoCarin
1 year agoReiko
1 year agoRusty
1 year agoWendell
1 year agoKallie
1 year ago