Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 4 Question 91 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 91
Topic #: 4
[All PMI-RMP Questions]

A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.

What should the risk manager advise the project manager?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Ruthann
2 days ago
I bet the risk manager is wishing they had a risk management plan that could handle the unexpected. Maybe they should have consulted a magic 8-ball instead.
upvoted 0 times
...
Monte
6 days ago
A is a cop-out. You can't just accept new risks without a proper plan. The risk manager needs to be proactive and address these issues.
upvoted 0 times
...
Ellsworth
13 days ago
D is the way to go. Escalating the new risks to the stakeholders is crucial to ensure proper communication and buy-in for the risk management process.
upvoted 0 times
...
Jaime
25 days ago
I think C is the best option. The risk manager should update the plan to reflect the new probabilities and impacts, and then adjust the response accordingly.
upvoted 0 times
...
Ashleigh
1 months ago
Option B seems like the most logical choice. The risk management plan should already have provisions for addressing any secondary risks that arise from the initial risk response.
upvoted 0 times
Nenita
3 days ago
C) Update the risk management plan with the new probability/impact and change the response.
upvoted 0 times
...
Carin
15 days ago
B) Address these secondary risks as per the risk management plan
upvoted 0 times
...
Reiko
19 days ago
B) Address these secondary risks as per the risk management plan
upvoted 0 times
...
...
Rusty
1 months ago
I believe the risk manager should also update the risk management plan with the new probability/impact and change the response accordingly.
upvoted 0 times
...
Wendell
2 months ago
I agree with Kallie. It's important to follow the risk management plan to mitigate any potential negative impacts on the project.
upvoted 0 times
...
Kallie
2 months ago
I think the risk manager should advise the project manager to address these secondary risks as per the risk management plan.
upvoted 0 times
...

Save Cancel