Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-RMP Exam - Topic 4 Question 112 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 112
Topic #: 4
[All PMI-RMP Questions]

The project sponsor asks the project manager about the accuracy of the project dat

a. The project manager realizes that some risks have not been updated recently.

What should the project manager do regarding those risks?

Show Suggested Answer Hide Answer
Suggested Answer: D

If the project manager realizes that some risks have not been updated recently, they should review the risk register to check for new risks and ensure that all risks are accurately documented and updated.

The risk register is a document that contains information about the identified risks, their analysis, and their response plans. It is updated throughout the project life cycle as new risks emerge, existing risks change, or risks are closed. The project manager should review the risk register regularly to ensure that the project data is accurate and reflects the current risk situation. Reviewing the risk register also helps the project manager to identify any new risks that may have occurred since the last update, and to plan appropriate responses for them.Reference:PMI, Project Risk Management, 2nd edition, 2019, p.67-681


Contribute your Thoughts:

0/2000 characters
Totally agree, updating the risks is a must!
upvoted 0 times
...
Deonna
5 days ago
Surprised that risks weren't updated recently, that's crucial!
upvoted 0 times
...
Daren
10 days ago
I think creating a risk response plan is more important.
upvoted 0 times
...
Arlette
15 days ago
Definitely review the risk register first!
upvoted 0 times
...
Alverta
21 days ago
I lean towards option D, reviewing the risk register, since it seems crucial to identify any new risks before taking further action.
upvoted 0 times
...
Devora
26 days ago
Conducting a checklist analysis sounds familiar, but I wonder if that really addresses the issue of outdated risks.
upvoted 0 times
...
Pedro
1 month ago
I remember a practice question where we had to create a risk response plan, but I feel like that might be too late if the risks haven't been updated.
upvoted 0 times
...
Pilar
1 month ago
I think the project manager should probably review the risk register, but I’m not entirely sure if that’s the best first step.
upvoted 0 times
...

Save Cancel