PMI-RMP Exam - Topic 2 Question 40 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 40
Topic #: 2
[All PMI-RMP Questions]

You are working as a project manager in your organization. You are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. For your project archives, which one of the following is an output of risk monitoring and control?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Hester
4 months ago
I remember learning that risk audits are key outputs!
upvoted 0 times
...
Alecia
4 months ago
Wait, are we sure about B? Seems too straightforward.
upvoted 0 times
...
Mabel
4 months ago
I'm not so sure, I thought it could be C, requested changes.
upvoted 0 times
...
Elmira
4 months ago
Totally agree, B is the right choice!
upvoted 0 times
...
Francoise
4 months ago
I think it's definitely B, risk audits.
upvoted 0 times
...
Gilbert
5 months ago
I think the answer is risk audits because they help ensure that we are on track with our risk management. But I could be wrong!
upvoted 0 times
...
Gladys
5 months ago
I feel like quantitative and qualitative risk analyses are more about initial assessments rather than outputs from monitoring. I’m confused about this one.
upvoted 0 times
...
Noel
5 months ago
I remember we discussed risk audits in class, but I'm not sure if they are considered an output. Could it be option B?
upvoted 0 times
...
Shaniqua
5 months ago
I think the output of risk monitoring and control might be related to changes we requested during the project. So, I'm leaning towards option C.
upvoted 0 times
...
Melvin
5 months ago
Hmm, this is a good one. I'll need to review my notes on Cisco collaboration device customization and the differences between JavaScript macros and external control systems. Gotta be ready for questions like this on the exam.
upvoted 0 times
...
Gaston
5 months ago
I'm a bit confused by the options. I'm not sure if an enterprise application in Azure AD or Active Directory Certificate Services would be the right solution here.
upvoted 0 times
...

Save Cancel