PMI-RMP Exam - Topic 2 Question 2 Discussion
Virginia is the project manager for her organization. She has hired a subject matter expert to interview the project stakeholders on certain identified risks within the project. The subject matter expert will assess the risk event with what specific goal in mind?
A) To determine the level of probability and impact for each risk event
B) To determine the bias of the risk event based on each person interviewed
C) To determine the probability and cost of the risk event
D) To determine the validity of each risk event