PMI-RMP Exam - Topic 10 Question 95 Discussion
A project team has completed plan risk response activities and has identified three critical risk response plans to major risk events. The responses have been monitored and implemented, with one of the responses presenting the two secondary risks.What should the risk manager do next?
B) Assess the impact of residual and secondary risks on project objectives.
A) Assess the risk register to ensure the secondary risks are realistic.
C) Assess the change log to establish that changes were implemented.
D) Assess the stakeholder register to determine the impact of initial risks.
Nina
6 months agoTonette
7 months agoWilford
7 months agoDalene
7 months agoSheron
7 months agoSabrina
7 months agoPeggy
8 months agoRoyal
8 months agoTwanna
8 months agoLeonie
8 months agoKenneth
8 months agoAlex
8 months agoFelix
8 months agoOliva
1 year agoMarti
1 year agoAlesia
1 year agoTheron
1 year agoBrianne
1 year agoBeckie
1 year agoJess
1 year agoMyrtie
1 year agoKris
1 year agoCristy
1 year agoMelvin
1 year agoMaricela
1 year agoSarah
1 year agoCaprice
1 year agoTerrilyn
1 year ago