PMI-RMP Exam - Topic 10 Question 95 Discussion
A project team has completed plan risk response activities and has identified three critical risk response plans to major risk events. The responses have been monitored and implemented, with one of the responses presenting the two secondary risks.What should the risk manager do next?
B) Assess the impact of residual and secondary risks on project objectives.
A) Assess the risk register to ensure the secondary risks are realistic.
C) Assess the change log to establish that changes were implemented.
D) Assess the stakeholder register to determine the impact of initial risks.
Nina
10 months agoTonette
10 months agoWilford
10 months agoDalene
10 months agoSheron
11 months agoSabrina
11 months agoPeggy
11 months agoRoyal
11 months agoTwanna
11 months agoLeonie
11 months agoKenneth
11 months agoAlex
11 months agoFelix
11 months agoOliva
2 years agoMarti
2 years agoAlesia
2 years agoTheron
2 years agoBrianne
2 years agoBeckie
2 years agoJess
2 years agoMyrtie
2 years agoKris
2 years agoCristy
2 years agoMelvin
2 years agoMaricela
2 years agoSarah
2 years agoCaprice
2 years agoTerrilyn
2 years ago