PMI-RMP Exam - Topic 10 Question 95 Discussion
A project team has completed plan risk response activities and has identified three critical risk response plans to major risk events. The responses have been monitored and implemented, with one of the responses presenting the two secondary risks.What should the risk manager do next?
B) Assess the impact of residual and secondary risks on project objectives.
A) Assess the risk register to ensure the secondary risks are realistic.
C) Assess the change log to establish that changes were implemented.
D) Assess the stakeholder register to determine the impact of initial risks.
Nina
8 months agoTonette
8 months agoWilford
8 months agoDalene
9 months agoSheron
9 months agoSabrina
9 months agoPeggy
9 months agoRoyal
9 months agoTwanna
10 months agoLeonie
10 months agoKenneth
10 months agoAlex
10 months agoFelix
10 months agoOliva
1 year agoMarti
2 years agoAlesia
2 years agoTheron
2 years agoBrianne
1 year agoBeckie
1 year agoJess
2 years agoMyrtie
1 year agoKris
1 year agoCristy
2 years agoMelvin
2 years agoMaricela
1 year agoSarah
2 years agoCaprice
2 years agoTerrilyn
2 years ago