Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 10 Question 92 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 92
Topic #: 10
[All PMI-RMP Questions]

During a project progress meeting, a project team member is concerned that one of the risks has triggered several other low-level risks. These risks should be responded to quickly or there will be severe consequences for the project deliverables.

What should the risk manager do?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Frederic
5 days ago
Performing a risk urgency assessment? That's like having a fire drill before the building's actually on fire. But hey, at least we'll be prepared, right?
upvoted 0 times
...
Makeda
9 days ago
B) Initiating a risk response when the risks occur? By then, it'll be too late! Gotta be proactive, not reactive. D) all the way, my friends.
upvoted 0 times
...
Carylon
10 days ago
C) Addressing only the high-priority risk? Seriously? That's like trying to plug a hole in a dam with a toothpick. We need a holistic approach here.
upvoted 0 times
...
Eugene
1 months ago
I agree, D) is the way to go. Addressing the root cause by assessing the urgency is crucial. Can't just put out fires, gotta prevent them!
upvoted 0 times
Suzan
7 days ago
D) Perform a risk urgency assessment.
upvoted 0 times
...
Coleen
9 days ago
B) Initiate a risk response when these risks occur.
upvoted 0 times
...
Krystina
18 days ago
A) Update the watchlist.
upvoted 0 times
...
...
Ashanti
1 months ago
Addressing only the high-priority risk may not be enough, we need to initiate a risk response when these risks occur to prevent severe consequences.
upvoted 0 times
...
Reuben
1 months ago
I think we should also perform a risk urgency assessment to prioritize which risks to address first.
upvoted 0 times
...
Ahmed
1 months ago
D) Performing a risk urgency assessment seems like the best approach here. We need to understand the full scope of the impact these risks could have on the project.
upvoted 0 times
Zita
16 days ago
B) Initiate a risk response when these risks occur.
upvoted 0 times
...
Hassie
18 days ago
A) Update the watchlist.
upvoted 0 times
...
...
Karol
1 months ago
We should update the watchlist to keep track of all the triggered risks.
upvoted 0 times
...

Save Cancel