A project baseline included a budget of USS900 million and a 12-month schedule. Three months into the project a risk manager collected performance data on the project expenditure showing an actual cumulative lost.
What should the risk manager use to ascertain the cost performance risk?
Yuette
23 days agoDerick
28 days agoMaybelle
2 months agoDierdre
2 months agoVerona
2 months agoVon
17 days agoJessenia
18 days agoRonnie
21 days agoPolly
24 days agoTarra
2 months agoFrance
2 months agoJerrod
2 months agoCiara
2 months agoNovella
2 months ago