Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 10 Question 69 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 69
Topic #: 10
[All PMI-RMP Questions]

A project baseline included a budget of USS900 million and a 12-month schedule. Three months into the project a risk manager collected performance data on the project expenditure showing an actual cumulative lost.

What should the risk manager use to ascertain the cost performance risk?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Maybelle
5 days ago
I'm not sure, but I think PESTLE analysis could also be useful in assessing the cost performance risk.
upvoted 0 times
...
Dierdre
6 days ago
I agree with Tarra, variance analysis would provide insights into the project's cost performance.
upvoted 0 times
...
Verona
9 days ago
PESTLE analysis? Really? That's like trying to fix a leaky faucet with a sledgehammer. Variance analysis is the way to go, no doubt about it.
upvoted 0 times
...
Tarra
11 days ago
I think the risk manager should use variance analysis to ascertain the cost performance risk.
upvoted 0 times
...
France
12 days ago
I'm not sure, but I think PESTLE analysis could also be useful in understanding the external factors affecting cost performance.
upvoted 0 times
...
Jerrod
12 days ago
Ah, variance analysis - the trusty tool to uncover the cost performance risk. Gotta love how it cuts through the data like a hot knife through butter!
upvoted 0 times
...
Ciara
14 days ago
I agree with Novella, variance analysis would be the best option to analyze the cost performance risk.
upvoted 0 times
...
Novella
17 days ago
I think the risk manager should use variance analysis to ascertain the cost performance risk.
upvoted 0 times
...

Save Cancel