PMI Exam PMI-RMP Topic 10 Question 69 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 69
Topic #: 10
[All PMI-RMP Questions]

A project baseline included a budget of USS900 million and a 12-month schedule. Three months into the project a risk manager collected performance data on the project expenditure showing an actual cumulative lost.

What should the risk manager use to ascertain the cost performance risk?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Yuette
23 days ago
Sentiment analysis? That's like using a crystal ball to predict the weather. Variance analysis is the way to go, folks. It's the Swiss Army knife of project management tools.
upvoted 0 times
...
Derick
28 days ago
Cluster analysis? What is this, a high school science fair project? Variance analysis is the only way to get a clear picture of the cost performance risk. Anything else is just a distraction.
upvoted 0 times
...
Maybelle
2 months ago
I'm not sure, but I think PESTLE analysis could also be useful in assessing the cost performance risk.
upvoted 0 times
...
Dierdre
2 months ago
I agree with Tarra, variance analysis would provide insights into the project's cost performance.
upvoted 0 times
...
Verona
2 months ago
PESTLE analysis? Really? That's like trying to fix a leaky faucet with a sledgehammer. Variance analysis is the way to go, no doubt about it.
upvoted 0 times
Von
17 days ago
Variance analysis is the way to go, no doubt about it.
upvoted 0 times
...
Jessenia
18 days ago
PESTLE analysis? Really? That's like trying to fix a leaky faucet with a sledgehammer.
upvoted 0 times
...
Ronnie
21 days ago
Variance analysis is the way to go, no doubt about it.
upvoted 0 times
...
Polly
24 days ago
PESTLE analysis? Really? That's like trying to fix a leaky faucet with a sledgehammer.
upvoted 0 times
...
...
Tarra
2 months ago
I think the risk manager should use variance analysis to ascertain the cost performance risk.
upvoted 0 times
...
France
2 months ago
I'm not sure, but I think PESTLE analysis could also be useful in understanding the external factors affecting cost performance.
upvoted 0 times
...
Jerrod
2 months ago
Ah, variance analysis - the trusty tool to uncover the cost performance risk. Gotta love how it cuts through the data like a hot knife through butter!
upvoted 0 times
...
Ciara
2 months ago
I agree with Novella, variance analysis would be the best option to analyze the cost performance risk.
upvoted 0 times
...
Novella
2 months ago
I think the risk manager should use variance analysis to ascertain the cost performance risk.
upvoted 0 times
...