PMI-RMP Exam - Topic 10 Question 15 Discussion

Posted by Karan on May 08, 2022 at 06:02 AM

You work as a project manager for TechSoft Inc. You are working with the project stakeholders on the qualitative risk analysis process in your project. You have used all the tools to the qualitative risk analysis process in your project. Which of the following techniques is NOT used as a tool in qualitative risk analysis process?

Suggested Answer: C

Get Premium PMI-RMP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
13 comments · newest first
CE
Cecilia 1 year ago
Risk Urgency Assessment is key in this process!
AN
Antonio 1 year ago
Risk Data Quality Assessment is definitely not qualitative.
MA
Maryanne 1 year ago
Wait, are we sure about that? I thought it was included.
JU
Juan 1 year ago
Totally agree, it's more of a quantitative thing!
CH
Chauncey 1 year ago
Risk Reassessment isn't part of qualitative analysis.
MO
Mohammad 1 year ago
I feel like all these options are related to risk management, but I can't pinpoint which one is not used in qualitative analysis.
WI
Winfred 1 year ago
I have a vague memory that Risk Data Quality Assessment might not be used in qualitative analysis, but I can't recall the details.
JE
Jennie 1 year ago
I think I remember that Risk Urgency Assessment is definitely part of qualitative risk analysis, but I'm not sure about Risk Reassessment.
JO
Josefa 1 year ago
I practiced a similar question where Risk Categorization was mentioned as a key tool, so I feel confident about that one.
JE
Jess 1 year ago
The correct answer has to be C - the model should be tailored to the specific organization being audited. That makes the most sense to me, as a one-size-fits-all approach wouldn't work well.
DI
Diane 1 year ago
I'm confident I can solve this. I just need to calculate the maximum line of credit utilization based on the cash flows and then apply the 1% interest rate.
PR
Providencia 1 year ago
Okay, I think I've got this. The key is to add the JavaScript library to the Events tab and the relevant fields to the non-event dependencies in both the Building code and Work item forms. This should ensure the library continues to function as designed, even if the environment is expanded.
VE
Veronika 1 year ago
Wait, what's the difference between response time and think time? I'm getting a bit confused by the wording of these options. Let me re-read the question and options carefully.
0/2000 characters

Save Cancel