Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-RMP Exam - Topic 1 Question 119 Discussion

A risk manager is preparing for the first meeting with their project sponsor on a potential project for a large client. The risk manager reviews their newly developed project risk register to identify any risks that should be analyzed further and begins by prioritizing the probability column based on the following criteria:1 = Very Low2 = Low3 = Medium4 = High5 = Very HighWhat type of risk analysis is the risk manager performing?
C) Qualitative risk analysis
A) Scenario-based risk analysis
B) Quantitative risk analysis
D) Monte Carlo analysis

PMI-RMP Exam - Topic 1 Question 119 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 119
Topic #: 1
[All PMI-RMP Questions]

A risk manager is preparing for the first meeting with their project sponsor on a potential project for a large client. The risk manager reviews their newly developed project risk register to identify any risks that should be analyzed further and begins by prioritizing the probability column based on the following criteria:

1 = Very Low

2 = Low

3 = Medium

4 = High

5 = Very High

What type of risk analysis is the risk manager performing?

Show Suggested Answer Hide Answer
Suggested Answer: C

The risk manager is performing a qualitative risk analysis by prioritizing risks based on their probability of occurrence. Qualitative risk analysis involves evaluating and prioritizing risks based on their likelihood and impact using a predefined scale. This approach helps in determining which risks require more attention and should be subjected to further analysis or immediate action.

PMI defines qualitative risk analysis as a process that uses a relative scale to assess the probability and impact of risks, which is what is being done in this scenario.


Contribute your Thoughts:

0/2000 characters
I remember practicing a question similar to this, and I think prioritizing risks like this usually points to qualitative analysis.
upvoted 0 times
...
Rosamond
5 days ago
I'm not entirely sure, but it seems like it could also be quantitative if they were using numbers to analyze impacts.
upvoted 0 times
...
Evangelina
10 days ago
I think the risk manager is doing a qualitative risk analysis since they are prioritizing risks based on probability ratings.
upvoted 0 times
...

Save Cancel