PMI-PBA Exam - Topic 8 Question 89 Discussion
A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch.The business analyst tells the stakeholder that the requirement status was changed to "deferred ''What could have prevented the stakeholder from being surprised about the status change?
B) The status should have been reviewed prior to project launch.
A) The status should have been communicated to the requirement's source.
C) The status should have been communicated to all project stakeholders.
D) The status should have been updated in the traceability matrix.
Hailey
6 months agoDarrin
6 months agoJovita
7 months agoShizue
7 months agoLaurel
7 months agoCeleste
7 months agoJamey
8 months agoNan
8 months agoEveline
8 months agoMarci
8 months agoElmer
8 months agoStefan
8 months agoShawnna
8 months agoCheryl
8 months agoCatrice
1 year agoMelinda
1 year agoAlethea
1 year agoMariann
12 months agoCarole
12 months agoEleonora
1 year agoMalika
1 year agoJudy
1 year agoSheridan
12 months agoMatthew
12 months agoLynelle
1 year agoJamika
1 year agoAlida
1 year agoJamika
1 year ago