PMI-PBA Exam - Topic 8 Question 89 Discussion
A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch.The business analyst tells the stakeholder that the requirement status was changed to "deferred ''What could have prevented the stakeholder from being surprised about the status change?
B) The status should have been reviewed prior to project launch.
A) The status should have been communicated to the requirement's source.
C) The status should have been communicated to all project stakeholders.
D) The status should have been updated in the traceability matrix.
Hailey
10 months agoDarrin
10 months agoJovita
10 months agoShizue
10 months agoLaurel
11 months agoCeleste
11 months agoJamey
11 months agoNan
11 months agoEveline
11 months agoMarci
11 months agoElmer
11 months agoStefan
11 months agoShawnna
11 months agoCheryl
11 months agoCatrice
1 year agoMelinda
1 year agoAlethea
1 year agoMariann
1 year agoCarole
1 year agoEleonora
1 year agoMalika
1 year agoJudy
1 year agoSheridan
1 year agoMatthew
1 year agoLynelle
1 year agoJamika
1 year agoAlida
1 year agoJamika
1 year ago