PMI-PBA Exam - Topic 7 Question 98 Discussion
A stakeholder has rejected a project's deliverable because it does not meet the original business need. It is further determined that the deliverable does not meet the requirements identified in the baseline.What is the best approach to resolve this issue?
B) Suggest re-estimating the requirement and following the change control process.
A) Meet with the customer and apologize for misunderstanding the business's need.
C) Provide the stakeholder with a copy of the approved requirements baseline and move forward without making a change.
D) Require development resources to work overtime to modify the deliverable to satisfy the stakeholder.
Mariko
5 months agoDannie
6 months agoAliza
6 months agoRoyce
6 months agoYun
6 months agoEnola
7 months agoCaitlin
7 months agoDesmond
7 months agoHoward
7 months agoDick
7 months agoAmira
8 months agoScarlet
8 months agoCrissy
8 months agoLucina
8 months agoScot
1 year agoYoulanda
1 year agoJanna
1 year agoYolando
1 year agoBernadine
1 year agoDevora
1 year agoTheola
1 year agoRory
1 year agoKristine
1 year agoCassi
1 year agoGearldine
1 year agoJohnson
1 year agoEstrella
1 year agoLai
1 year agoCristina
1 year agoWillard
1 year agoTwana
1 year agoJani
1 year agoMaynard
1 year agoRessie
1 year ago