What are some of the components of a requirements management plan?
C) Requirements work plan, prioritization process, and traceability matrix template
A) Requirements work plan, requirements definition, and traceability matrix template
B) Requirements definition, functional and non-functional requirements, and decision-making process
D) Requirements definition, requirements attribute template, and traceability matrix template