Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-PBA Exam - Topic 1 Question 120 Discussion

Which statement accurately depicts what changes can be made to requirements after they are baselined?
B) Requirements can be changed through a defined process.
A) Requirements can be changed only with sponsor approval.
C) Requirements cannot be changed once development begins.
D) Requirements cannot be changed once user acceptance testing begins.

PMI-PBA Exam - Topic 1 Question 120 Discussion

Actual exam question for PMI's PMI-PBA exam
Question #: 120
Topic #: 1
[All PMI-PBA Questions]

Which statement accurately depicts what changes can be made to requirements after they are baselined?

Show Suggested Answer Hide Answer
Suggested Answer: B

Requirements baseline is the approved version of the requirements document that serves as a reference point for further changes. Requirements can be changed after they are baselined through a defined process that involves submitting a change request, analyzing the impact of the change, obtaining approval from the stakeholders, updating the requirements document, and communicating the change to the project team and other affected parties. Requirements can be changed at any stage of the project life cycle as long as they follow the defined process.Reference: = PMI Professional in Business Analysis (PMI-PBA) Examination Content Outline (2019), page 10; Business Analysis for Practitioners: A Practice Guide (2015), page 40.


Contribute your Thoughts:

0/2000 characters
Lavonne
22 hours ago
I agree with Alice. A defined process keeps things organized.
upvoted 0 times
...
Malcolm
6 days ago
I think B is the best answer. Changes should follow a process.
upvoted 0 times
...
Staci
11 days ago
I thought once baselined, nothing could change. Surprised by this!
upvoted 0 times
...
Weldon
16 days ago
Wait, D? That seems too limiting. What if issues come up?
upvoted 0 times
...
Ardella
22 days ago
C is too strict. Changes can happen anytime if needed.
upvoted 0 times
...
Demetra
27 days ago
I disagree, A makes sense too. Sponsor approval is key!
upvoted 0 times
...
Melissa
1 month ago
B is the right answer. There’s always a process for changes.
upvoted 0 times
...
Billy
1 month ago
I recall that changes can happen, but there are rules around it. B sounds familiar, but I’m not completely confident.
upvoted 0 times
...
Aide
1 month ago
I practiced a question like this before, and I think it was about needing sponsor approval for changes. So, A might be right?
upvoted 0 times
...
Barbra
2 months ago
I'm not entirely sure, but I feel like once development starts, changes are really limited. Could it be C?
upvoted 0 times
...
Isabelle
2 months ago
I think I remember that requirements can be changed, but only through a specific process. So, maybe B?
upvoted 0 times
...

Save Cancel