Which statement accurately depicts what changes can be made to requirements after they are baselined?
B) Requirements can be changed through a defined process.
A) Requirements can be changed only with sponsor approval.
C) Requirements cannot be changed once development begins.
D) Requirements cannot be changed once user acceptance testing begins.

PMI-PBA Exam - Topic 1 Question 120 Discussion

Actual exam question for PMI's PMI-PBA exam
Question #: 120
Topic #: 1
[All PMI-PBA Questions]

Which statement accurately depicts what changes can be made to requirements after they are baselined?

Show Suggested Answer Hide Answer
Suggested Answer: B

Requirements baseline is the approved version of the requirements document that serves as a reference point for further changes. Requirements can be changed after they are baselined through a defined process that involves submitting a change request, analyzing the impact of the change, obtaining approval from the stakeholders, updating the requirements document, and communicating the change to the project team and other affected parties. Requirements can be changed at any stage of the project life cycle as long as they follow the defined process.Reference: = PMI Professional in Business Analysis (PMI-PBA) Examination Content Outline (2019), page 10; Business Analysis for Practitioners: A Practice Guide (2015), page 40.


Contribute your Thoughts:

0/2000 characters
Barbra
2 days ago
I'm not entirely sure, but I feel like once development starts, changes are really limited. Could it be C?
upvoted 0 times
...
Isabelle
7 days ago
I think I remember that requirements can be changed, but only through a specific process. So, maybe B?