A team's technical lead believes that manual testing tasks should be conducted by junior team members below their level. The junior team members think it is unfair and refuse the tasks.What should the scrum master do?
B) Facilitate an open and focused team discussion that reinforces team agreements.
A) Tell the technical lead to do the testing.
C) Ask the team manager to advise the technical lead that all tasks are important.
D) Encourage the team to take ownership of the delivery.