When introducing agile processes to a company, a quality assurance (QA) manager resists and believes that the switch to agile will remove quality controls and documents.
How should the agile practitioner address this concern?
The correct answer is A -- Educate the QA manager that in agile, quality is integrated from the beginning to the end of the project. Agile emphasizes ''built-in'' quality through test-first approaches, continuous integration, and Definition of Done. Addressing resistance through education helps clarify that quality is a core part of Agile---not an afterthought.
From the PMI Agile Practice Guide:
''Agile does not remove quality controls; rather, it integrates them throughout the development process. Quality is everyone's responsibility and is embedded through practices such as TDD, automated testing, and continuous feedback.''
(PMI Agile Practice Guide, Section 3.5 -- Quality and Agile)
Mike Griffiths adds:
''In Agile, quality is not sacrificed. It is a fundamental principle. Teams ensure quality by defining acceptance criteria, using continuous integration, and practicing test-first development.''
(Mike Griffiths, PMI-ACP Exam Prep, Chapter 3 -- Value-Driven Delivery)
Incorrect options:
B may be helpful tactically, but doesn't address the underlying concern.
C misrepresents technical debt.
D places too much QA responsibility on the product owner.
Answe r: A
A new product owner needs to manage the backlog of a high-visibility, fast-moving project that is consuming a considerable amount of time.
What should the product owner do?
The correct answer is C -- Seek regular input from project stakeholders, and reflect this input in the backlog's priorities. Agile is a stakeholder-driven process, and backlog refinement should be informed by continuous feedback. The product owner maximizes value by regularly reviewing stakeholder needs and reprioritizing accordingly.
From the PMI Agile Practice Guide:
''The product owner is responsible for maintaining the backlog and ensuring it reflects stakeholder priorities. Ongoing engagement with stakeholders ensures the product delivers maximum value.''
(PMI Agile Practice Guide, Section 5.2 -- Product Backlog Management)
Mike Griffiths adds:
''Agile product owners engage stakeholders continuously to update priorities and deliver value incrementally.''
(Mike Griffiths, PMI-ACP Exam Prep, Chapter 3 -- Value-Driven Delivery)
Incorrect options:
A is good practice but doesn't address the stakeholder engagement challenge.
B confuses story size with business value.
D lacks the agility required in a fast-moving project.
Answe r: C
A key resource is switching between projects to obtain more visibility and acclaim. However, project work has grown and become a burden.
What should the agile project leader do?
The correct answer is C --- Ask management to ensure that the resource is available to only one project at a time.
Agile promotes dedicated, stable teams over multitasking. Task-switching reduces productivity and leads to context-switching overhead. If a key resource is overburdened and switching between multiple projects, the best solution is to secure focused commitment by escalating to management for support.
PMI Agile Practice Guide:
''Agile teams should be dedicated and work on one project at a time. Splitting attention across multiple efforts reduces velocity and quality due to context switching.''
(PMI Agile Practice Guide, Section 6.1 -- Team Composition)
Mike Griffiths highlights:
''Effective agile teams are stable, long-lived, and dedicated. Shared resources create bottlenecks, undermine predictability, and impair team dynamics.''
(PMI-ACP Exam Prep, Chapter 4 -- Team Performance)
Incorrect options:
A may solve bandwidth issues but not focus or ownership.
B addresses symptoms, not the core issue of divided focus.
D tolerates a harmful practice that contradicts agile team stability.
Answe r: C
What should the agile project manager do?
Gold-plating---adding extra features not requested or prioritized---is an anti-pattern in agile. Agile emphasizes delivering the highest-priority features first, and product changes should always go through the Product Owner for prioritization and validation.
According to the PMI Agile Practice Guide (Section 5.1: Backlog and Value Delivery) and Mike Griffiths' PMI-ACP Exam Prep Book (Chapter 6: Value-Driven Delivery), when capacity is available, the team should pull more stories from the prioritized backlog, ensuring that all work aligns with stakeholder-defined value.
Option D is correct: confirm backlog priority and use time to deliver customer-prioritized value.
Option A supports scope creep.
Option B is partially correct but doesn't optimize the time to deliver value.
Option C perpetuates gold-plating and undermines value alignment.
The manager of the team is responsible for delivering a specific initiative within the organization. They are preparing for the monthly project review meeting, where they will present the current state of this initiative. The agile project lead sends the manager the following email with the initiative's current status.
Which summaries are correct and will be presented during the monthly project review? (Refer to
the email and exhibits to the Team Manager)
Step 1: Identifying Remaining MVP Story Points
From the backlog, the MVP-related stories that are not started include:



Total remaining MVP story points = 4 + 21 + 5 = 30
Step 2: Projected Sprint Completion



Sakura Liu
25 days agoDavid Hernandez
1 month agoMinhee Tanaka
2 months agoKenneth Thomas
2 months agoJames Green
3 months agoSteven Martinez
3 months agoAmanda Jones
4 months agoBrian Sanchez
5 months agoBarbara Turner
5 months agoRonald Flores
6 months agoJennifer Thompson
25 days agoAndrew Stewart
6 months agoCarol Garcia
5 months agoKevin Nguyen
5 months agoDeborah Williams
5 months agoKing
7 months agoJesus
7 months agoJulieta
7 months agoJosphine
7 months agoSage
7 months agoLoren
8 months agoLuisa
8 months agoMari
8 months agoLavera
8 months agoJohana
9 months agoWayne
9 months agoLavonda
9 months agoMarcelle
9 months agoBuck
10 months agoLavonda
10 months agoMagnolia
10 months agoBilli
10 months agoZack
11 months agoKarina
11 months agoFranchesca
11 months agoMalika
11 months agoMarylyn
12 months agoWilson
12 months agoElly
1 year agoEloisa
1 year agoCarmela
1 year agoDorsey
1 year agoGeorgene
1 year agoTesha
1 year agoSalena
1 year agoYuriko
1 year agoHaydee
1 year agoShonda
2 years agoLai
2 years agoMy
2 years agoFrank
2 years agoColette
2 years agoKarma
2 years agoSalome
2 years agoLorrine
2 years agoWei
2 years agoNieves
2 years agoEladia
2 years agoCharisse
2 years agoPatti
2 years agoMammie
2 years agoJeff
2 years agoKayleigh
2 years agoFelix
2 years agoCarolynn
2 years agoStanton
2 years agoDanica
2 years agoCiara
2 years agoEllsworth
2 years agoTasia
2 years agoVerdell
2 years agoJoaquin
2 years agoErasmo
2 years agoMaybelle
2 years agoLeonora
2 years agoHermila
2 years agoChu
2 years agoBrittney
2 years agoElena
2 years ago