Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-ACP Topic 8 Question 73 Discussion

Actual exam question for PMI's PMI Agile Certified Practitioner exam
Question #: 73
Topic #: 8
[All PMI Agile Certified Practitioner Questions]

A projects first iteration contains item

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Lera
12 days ago
Hmm, I'm not so sure. Option B does seem tempting, especially if we're already behind schedule. But I agree, we need to be careful about scope creep. Maybe we could compromise and do a bit of preliminary design on item B, just to get a head start, but not fully commit to it until the second iteration?
upvoted 0 times
...
Corrina
13 days ago
You know, I was just thinking the same thing. Deferring the design of item B is probably the safest bet. We don't want to end up in a situation where we're trying to cram too much in and end up with a subpar product.
upvoted 0 times
Arlene
6 hours ago
A) Defer starting the design of item B until the second iteration is being planned
upvoted 0 times
...
...
Stevie
14 days ago
I agree, this is a tough one. On the one hand, we want to try and stay on schedule, but on the other, we don't want to risk the quality of the deliverables. Maybe we should consider option A and defer the design of item B until the second iteration is being planned.
upvoted 0 times
...
Alberta
15 days ago
Hmm, this is a tricky one. I can see the logic behind starting the design of item B early to try and catch up, but I'm not sure that's the best approach. We need to be careful about scope creep and making sure we don't overcommit ourselves.
upvoted 0 times
...

Save Cancel