An agile coach is assigned to help a project learn that was recently co-located dose to a very popular business Many team members visit this business during working hours which affects team performance What should the agile coach do to mitigate this issue?
C) Meet with the team to discuss the issue and identify specific actions to reduce or eliminate the issue
A) Speak with the functional managers and come to an agreement that will resolve the issue
B) Explain to functional managers that too much control will inversly impact team morale
D) inform the team there will be penalties to anyone who visits that business during working hours