PMI-ACP Exam - Topic 8 Question 52 Discussion
An agile team member identifies a potential problem within the project team How should the team's coach react?
C) Instruct the team to try to solve the problem within the team
A) Document the problem escalate to the project manager, and develop a solution for the team
B) Add the problem to the backlog and assign resolution to a future iteration
D) Perform root cause analysis and report the problem to the product owner