PMI-ACP Exam - Topic 7 Question 8 Discussion
A team member has spent 5 days on a spike and the first set of experiments has not been successful The issue is the development team member has determined a short-term rather than a long-term solution.What should the project leader do?
B) Re-establish the spike, encourage experimentation and collaborate with the team.
A) Assign the spike to another resource to continue research for the long-term solution
C) Stop experimentation and negotiate the short-term solution with the customer.
D) Schedule a root-cause analysis with the development team on the mam issues with the spike
Shelba
7 months agoAbel
7 months agoGraham
7 months agoDana
8 months agoKaran
8 months agoRyan
8 months agoRebeca
8 months agoChandra
8 months agoSantos
8 months agoMichael
8 months agoLavonna
8 months agoMargarita
8 months agoBambi
8 months agoChandra
8 months ago