New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-ACP Exam - Topic 5 Question 91 Discussion

Actual exam question for PMI's PMI-ACP exam
Question #: 91
Topic #: 5
[All PMI-ACP Questions]

Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint. Team B estimates 280 story points for scope and 20 story points for velocity per sprint. Both teams have same number of team members and have an assumed sprint duration of 2 weeks.

What can an agile practitioner conclude about team A and team B's estimates?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Chau
3 months ago
Not sure about that, but both teams should clarify their tech choices first!
upvoted 0 times
...
Vashti
3 months ago
Wait, how can both teams have the same number of members but such different estimates?
upvoted 0 times
...
Lorrie
3 months ago
Team A seems more confident in their velocity for sure.
upvoted 0 times
...
Shannon
4 months ago
I think Team B's scope is definitely underestimated.
upvoted 0 times
...
Hana
4 months ago
Team A has way more story points than Team B.
upvoted 0 times
...
Lorean
4 months ago
Both teams have different story point estimates, so I don't think they see the project as the same size, right?
upvoted 0 times
...
Mireya
4 months ago
I feel like the technology used could really impact the estimates, but I can't recall if we need that info to analyze the estimates properly.
upvoted 0 times
...
Samuel
4 months ago
I'm not sure, but I think we had a practice question where underestimating scope led to issues later on. Could that apply here with Team B?
upvoted 0 times
...
Louisa
5 months ago
I remember we discussed how velocity can indicate confidence, so maybe Team A really believes they can deliver more than Team B.
upvoted 0 times
...
Rex
5 months ago
Based on the information provided, it seems like Team B has underestimated the scope compared to Team A. I'll make sure to carefully compare the estimates to identify any potential issues.
upvoted 0 times
...
Katina
5 months ago
Okay, let's see. Team A has a higher scope estimate but also a higher velocity per sprint. Team B has lower estimates all around. I'd say Team A is more confident in their ability to deliver.
upvoted 0 times
...
Roy
5 months ago
I'm a bit confused by the different story point estimates. Do we need more information about the teams' experience or the project requirements to really analyze this?
upvoted 0 times
...
Ernestine
5 months ago
Hmm, this seems straightforward. I think I can compare the scope and velocity estimates to determine which team is more confident in their delivery.
upvoted 0 times
...
Bobbie
9 months ago
Ah, I see the teams are playing a game of 'my estimate is bigger than yours.' Someone call the project management Olympics, we've got a winner!
upvoted 0 times
...
Micaela
9 months ago
Well, if both teams have the same number of members and sprint duration, then the difference in their estimates must mean they've sized the project differently. Option D seems to be the most logical conclusion.
upvoted 0 times
...
Myrtie
9 months ago
I'm not sure proposed technology has much to do with these estimates. The question clearly states the teams have the same number of members and sprint duration, so I don't think Option C is the correct answer here.
upvoted 0 times
...
Dusti
10 months ago
Team A's velocity estimate of 30 story points per sprint is higher than Team B's 20 story points per sprint, so Team A does seem more confident in their ability to deliver velocity. Option B is the right choice.
upvoted 0 times
Jimmie
8 months ago
B) Team A is more confident in delivering velocity than team B.
upvoted 0 times
...
Nu
9 months ago
A) Team B has underestimated scope compared to team A.
upvoted 0 times
...
...
Brittni
11 months ago
Team A's estimate of 420 story points for scope is significantly higher than Team B's 280 story points, so it's clear that Team B has underestimated the scope in comparison to Team A. Option A is the correct answer here.
upvoted 0 times
Maybelle
9 months ago
Team A is more confident in delivering velocity than team B.
upvoted 0 times
...
Alva
9 months ago
Team A's estimate of 420 story points for scope is significantly higher than Team B's 280 story points, so it's clear that Team B has underestimated the scope in comparison to Team A.
upvoted 0 times
...
...
Terina
11 months ago
But Team B has a lower velocity per sprint, so they might struggle to deliver on time.
upvoted 0 times
...
Dottie
11 months ago
I agree with you, Pamella. Team A's higher story points for scope indicate that.
upvoted 0 times
...
Pamella
11 months ago
I think Team A has estimated a larger scope than Team B.
upvoted 0 times
...

Save Cancel