An agile project manager is planning the initial scope schedule, and cost range estimates on a new project. The team will be using Kanban to control work What metrics should the team use to measure performance?
A) Lead time throughput and due date performance
B) Work m progress limits Kanban board and time boxes
C) Work item types, sprint cadences, and detect classes
D) Burndown charts, scatter diagrams and throughput