PMI-ACP Exam - Topic 4 Question 4 Discussion
An agile team identifies that their velocity is lower than predicted, and that their previous forecasts in the product roadmap are wrong. The team is worried that they will be unable to meet a critical release date without corrective action.What should the team do?
A) Collaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed before the release.
B) Ask the team lead to calculate the team's target velocity according to the project plan, and assign additional resources to increase capacity.
C) Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans.
D) Reestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations.
Theola
10 months agoBrock
11 months agoLaine
11 months agoJustine
11 months agoGracia
11 months agoJeannetta
11 months agoAdaline
11 months agoVan
11 months agoJanella
11 months agoSylvie
12 months agoDallas
12 months agoNatalya
12 months agoGail
12 months agoShala
12 months agoCheryll
12 months agoFelix
12 months ago