PMI-ACP Exam - Topic 4 Question 4 Discussion
An agile team identifies that their velocity is lower than predicted, and that their previous forecasts in the product roadmap are wrong. The team is worried that they will be unable to meet a critical release date without corrective action.What should the team do?
A) Collaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed before the release.
B) Ask the team lead to calculate the team's target velocity according to the project plan, and assign additional resources to increase capacity.
C) Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans.
D) Reestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations.
Theola
9 months agoBrock
9 months agoLaine
9 months agoJustine
9 months agoGracia
9 months agoJeannetta
10 months agoAdaline
10 months agoVan
10 months agoJanella
10 months agoSylvie
10 months agoDallas
10 months agoNatalya
10 months agoGail
10 months agoShala
10 months agoCheryll
10 months agoFelix
10 months ago