PMI-ACP Exam - Topic 4 Question 100 Discussion

Toward the end of a project, the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected. What should the product owner do?
D) Continue the project, release the product without the failing feature, and fix the feature in a subsequent release.
A) Terminate the project to cut losses.
B) Review possible options and make an informed decision to cut losses based on delivered business value.
C) Bring in experts to increase the probability of success.

PMI-ACP Exam - Topic 4 Question 100 Discussion

Actual exam question for PMI's PMI-ACP exam
Question #: 100
Topic #: 4
[All PMI-ACP Questions]

Toward the end of a project, the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected. What should the product owner do?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Mertie
5 months ago
Definitely bring in experts, option C all the way!
upvoted 0 times
...
Lorean
6 months ago
I disagree, terminating might be too hasty.
upvoted 0 times
...
Darrin
6 months ago
Option B seems the most logical. Gotta weigh the value.
upvoted 0 times
...
Josphine
6 months ago
Cutting losses is smart, but what about the impact on users?
upvoted 0 times
...
Shay
6 months ago
Surprised that some would suggest continuing without the feature!
upvoted 0 times
...
Ilene
7 months ago
I vaguely recall that terminating a project can be a tough call. I wonder if option A is too drastic without exploring other options first.
upvoted 0 times
...
Jodi
7 months ago
I’m a bit torn between options B and D. I know releasing without the feature could be risky, but sometimes it’s better to get something out there.
upvoted 0 times
...
Marion
7 months ago
I think we practiced a similar scenario where we had to decide whether to cut losses or push through. I feel like bringing in experts could help, so maybe option C is worth considering.
upvoted 0 times
...
Tabetha
7 months ago
I remember discussing the importance of assessing business value in class. Option B seems like a reasonable approach, but I'm not entirely sure if it's the best choice.
upvoted 0 times
...
Jacquline
7 months ago
I'm not sure, this is a tough call. I'll need to review the details and consult with the team before making a decision.
upvoted 0 times
...
Lorita
8 months ago
Terminating the project might be the safest option, but I'd hate to lose all the work we've done so far. I'll have to think this through.
upvoted 0 times
...
Thea
8 months ago
I think bringing in experts is the way to go here. We need to do everything we can to increase the chances of success.
upvoted 0 times
...
Gwen
8 months ago
Okay, let's see... I'm leaning towards option B, but I want to make sure I understand all the implications before deciding.
upvoted 0 times
...
Tess
8 months ago
Hmm, this is a tricky one. I'll need to carefully weigh the options and consider the potential impact on the business.
upvoted 0 times
...
Salome
1 year ago
I'm going with B. It's like playing a game of 'Would You Rather' - do you want to lose big or lose small? I choose small!
upvoted 0 times
Wilbert
11 months ago
D: The product owner should abandon the project altogether.
upvoted 0 times
...
Aja
1 year ago
C: The product owner should ignore the issue and hope for the best.
upvoted 0 times
...
Denna
1 year ago
B: The product owner should assess the impact of the critical feature not functioning and come up with a plan to mitigate the risk.
upvoted 0 times
...
Alecia
1 year ago
A: The product owner should immediately communicate the issue to the team and stakeholders.
upvoted 0 times
...
...
Latricia
1 year ago
A is the easy way out, but let's be honest, who likes cutting their losses? Not this guy! Let's try to salvage this thing.
upvoted 0 times
...
Cordell
1 year ago
C seems like the safest bet. Bringing in the experts can really save the day, though it might cost an arm and a leg.
upvoted 0 times
Earleen
12 months ago
C) Bring in experts to increase the probability of success.
upvoted 0 times
...
Lisandra
12 months ago
B) Review possible options and make an informed decision to cut losses based on delivered business value.
upvoted 0 times
...
Kimbery
1 year ago
A) Terminate the project to cut losses.
upvoted 0 times
...
...
Gilbert
1 year ago
I agree with Pearly. Bringing in experts could help salvage the project.
upvoted 0 times
...
Pearly
1 year ago
I think they should bring in experts to increase the probability of success.
upvoted 0 times
...
Amos
1 year ago
D is the riskiest option, but sometimes you gotta do what you gotta do to get the product out the door. I hope the users have a good sense of humor!
upvoted 0 times
Johnetta
12 months ago
User 3: Hopefully users will understand and appreciate the effort to fix it in the next release.
upvoted 0 times
...
Lashawnda
1 year ago
User 2: Yeah, it's risky but sometimes you have to prioritize getting the product out.
upvoted 0 times
...
Jackie
1 year ago
User 1: Let's just release the product without the failing feature and fix it later.
upvoted 0 times
...
...
Valene
1 year ago
I think B is the way to go. Reviewing options and making an informed decision based on delivered value is the most prudent approach.
upvoted 0 times
Adelle
1 year ago
In the end, it's about making the best decision for the project.
upvoted 0 times
...
Ula
1 year ago
That's true, experts might increase the chances of success.
upvoted 0 times
...
Kate
1 year ago
But what if bringing in experts could help salvage the project?
upvoted 0 times
...
Nina
1 year ago
I agree, cutting losses based on delivered business value is important.
upvoted 0 times
...
...
Marjory
1 year ago
What should the product owner do if a critical feature is not functioning as expected?
upvoted 0 times
...

Save Cancel