PMI-ACP Exam - Topic 3 Question 119 Discussion

Posted by Lorrie on Jun 30, 2026 at 11:00 AM

The manager of the team is responsible for delivering a specific initiative within the organization. They are preparing for the monthly project review meeting, where they will present the current state of this initiative. The agile project lead sends the manager the following email with the initiative's current status.

Which summaries are correct and will be presented during the monthly project review? (Refer to

the email and exhibits to the Team Manager)

Suggested Answer: D

Step 1: Identifying Remaining MVP Story Points

From the backlog, the MVP-related stories that are not started include:

Total remaining MVP story points = 4 + 21 + 5 = 30

Step 2: Projected Sprint Completion


Get Premium PMI-ACP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
21 comments · newest first
HE
Herman 2 days ago
I vote for C. 25 points, but end of sprint 9.
NE
Nenita 7 days ago
True, but it fits the timeline better.
LO
Lonna 12 days ago
But B has 30, not 25.
NE
Nenita 17 days ago
I prefer B. It has 30 points, sounds right.
CH
Cherelle 23 days ago
It matches the story points and sprint completion.
LO
Lonna 28 days ago
Why A?
CH
Cherelle 1 month ago
I think A is correct.
CY
Cyril 1 month ago
I think C makes more sense with the timeline!
VI
Vivienne 1 month ago
B is wrong, it should be 25 points, not 30.
TH
Thurman 2 months ago
Wait, how can we be sure about the backlog completion?
TE
Temeka 2 months ago
Totally agree, looks like we're on track for sprint 8.
DO
Dolores 2 months ago
A is correct, 25 story points left!
LA
Lauryn 2 months ago
I’m surprised the backlog completion is so far out!
ET
Ettie 2 months ago
C seems off, we need to double-check those numbers.
CY
Cyndy 2 months ago
Wait, how can the MVP finish in sprint 9 if it has 30 points?
RA
Raylene 3 months ago
I think B is more accurate, though.
GE
Gertude 3 months ago
A has 25 story points, sounds right!
CE
Celia 3 months ago
I recall that the completion dates can shift based on the story points. I might lean towards option D, but I need to double-check the details.
SI
Silvana 3 months ago
I’m a bit confused about the story points. I thought the MVP had 30 remaining, but now I’m not so sure.
DI
Diego 3 months ago
I remember practicing with similar questions, and I feel like the completion dates are key. I think it could be option C.
AH
Ahmed 4 months ago
I think option A sounds familiar, but I'm not entirely sure about the remaining story points. Was it 25 or 30?