Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-ACP Exam - Topic 3 Question 119 Discussion

The manager of the team is responsible for delivering a specific initiative within the organization. They are preparing for the monthly project review meeting, where they will present the current state of this initiative. The agile project lead sends the manager the following email with the initiative's current status.Which summaries are correct and will be presented during the monthly project review? (Refer tothe email and exhibits to the Team Manager)
D) MVP has 30 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.
A) MVP has 25 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.
B) MVP has 30 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.
C) MVP has 25 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.

PMI-ACP Exam - Topic 3 Question 119 Discussion

Actual exam question for PMI's PMI-ACP exam
Question #: 119
Topic #: 3
[All PMI-ACP Questions]

The manager of the team is responsible for delivering a specific initiative within the organization. They are preparing for the monthly project review meeting, where they will present the current state of this initiative. The agile project lead sends the manager the following email with the initiative's current status.

Which summaries are correct and will be presented during the monthly project review? (Refer to

the email and exhibits to the Team Manager)

Show Suggested Answer Hide Answer
Suggested Answer: D

Step 1: Identifying Remaining MVP Story Points

From the backlog, the MVP-related stories that are not started include:

Total remaining MVP story points = 4 + 21 + 5 = 30

Step 2: Projected Sprint Completion


Contribute your Thoughts:

0/2000 characters
Thurman
3 days ago
Wait, how can we be sure about the backlog completion?
upvoted 0 times
...
Temeka
8 days ago
Totally agree, looks like we're on track for sprint 8.
upvoted 0 times
...
Dolores
14 days ago
A is correct, 25 story points left!
upvoted 0 times
...
Lauryn
19 days ago
I’m surprised the backlog completion is so far out!
upvoted 0 times
...
Ettie
24 days ago
C seems off, we need to double-check those numbers.
upvoted 0 times
...
Cyndy
29 days ago
Wait, how can the MVP finish in sprint 9 if it has 30 points?
upvoted 0 times
...
Raylene
1 month ago
I think B is more accurate, though.
upvoted 0 times
...
Gertude
1 month ago
A has 25 story points, sounds right!
upvoted 0 times
...
Celia
1 month ago
I recall that the completion dates can shift based on the story points. I might lean towards option D, but I need to double-check the details.
upvoted 0 times
...
Silvana
2 months ago
I’m a bit confused about the story points. I thought the MVP had 30 remaining, but now I’m not so sure.
upvoted 0 times
...
Diego
2 months ago
I remember practicing with similar questions, and I feel like the completion dates are key. I think it could be option C.
upvoted 0 times
...
Ahmed
2 months ago
I think option A sounds familiar, but I'm not entirely sure about the remaining story points. Was it 25 or 30?
upvoted 0 times
...

Save Cancel