Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-ACP Topic 2 Question 98 Discussion

Actual exam question for PMI's PMI-ACP exam
Question #: 98
Topic #: 2
[All PMI-ACP Questions]

Exhibit:

Based on the backlog metrics in the chart, what can explain the Jump in points at the end of iteration 4?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Pamella
2 months ago
Haha, I bet the team was like, 'Oops, looks like we messed up the estimations! Time to play 'Let's Make a Deal' with the backlog!'
upvoted 0 times
Jesusita
9 days ago
D) The team learned that the product owner needed to increase the output in the next release
upvoted 0 times
...
Justine
11 days ago
C) The team realized that some stories were underestimated relative to other stones and reestimated as needed
upvoted 0 times
...
Sylvia
16 days ago
B) The team discovered that previously accepted work could be greatly improved and added story points associated with that work
upvoted 0 times
...
Pansy
28 days ago
A) The team neglected to account for support and maintenance costs associated with other supported products
upvoted 0 times
...
...
Leota
2 months ago
I agree, Option C makes the most sense. It's common for teams to discover underestimated stories and need to adjust the points accordingly.
upvoted 0 times
...
Devora
2 months ago
Option C looks like the correct answer here. The team probably realized that some stories were underestimated and needed to re-estimate them.
upvoted 0 times
Leandro
20 days ago
It's important for teams to adjust estimates as they learn more about the work involved.
upvoted 0 times
...
Verlene
22 days ago
I think the team must have re-estimated the stories to reflect their actual complexity.
upvoted 0 times
...
Buddy
23 days ago
Agreed, option C seems to be the most logical explanation for the jump in points.
upvoted 0 times
...
...
Ronnie
2 months ago
That's a good point, Alberta. Improvements in work could definitely lead to added story points.
upvoted 0 times
...
Alberta
2 months ago
I believe the team might have discovered improvements in previously accepted work.
upvoted 0 times
...
Ellen
2 months ago
I agree with Ronnie, underestimation of stories could explain the increase in points.
upvoted 0 times
...
Ronnie
3 months ago
I think the jump in points could be due to underestimation of some stories.
upvoted 0 times
...

Save Cancel