PMI-ACP Exam - Topic 2 Question 56 Discussion
Midway through a sprint the scrum master identifies that reassigning a certain task could help the team meet its sprint goals. What should the scrum master do next?
B) Obtain team buy-in to perform modifications to the sprint backlog
A) Alert the team that sprint goals might not be met and create an alternative plan
C) Have the sprint proceed as planned
D) Ask the team to decide if the task should be reassigned