Trend analysis shows that velocity is significantly higher than predicted and the release can be completed one month ahead of schedule. The team recommends changing the end date to reflect this What should the agile practitioner do?

Suggested Answer: A

Get Premium PMI-ACP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
14 comments · newest first
IZ
Izetta 1 year ago
Changing the end date could really boost team morale!
IS
Isabella 1 year ago
I think option B is too hasty, we need to discuss first.
SA
Sanda 1 year ago
Wait, can we really trust those velocity numbers?
WI
Willard 1 year ago
Definitely agree, option A is the way to go.
HE
Helene 1 year ago
Sounds like a good opportunity to adjust the timeline!
ED
Eden 1 year ago
I really hope we don't go with option D. Asking the team to decrease velocity feels counterproductive and goes against agile principles.
CH
Christa 1 year ago
I feel like we practiced a similar question where we had to balance velocity and backlog priorities. Option C might be tempting, but it could complicate things.
AL
Alline 1 year ago
I'm not entirely sure, but I think just announcing the new end date without discussion could lead to misunderstandings.
LO
Louisa 1 year ago
I remember we discussed the importance of involving the team and product owner in decision-making, so option A seems right.
ST
Stephanie 1 year ago
I'm thinking we'll need a combination of servers here. The mail server for the email functions, plus maybe an FTP server for the file transfer and access, and potentially a DNS server to handle the domain name access.
KI
Kindra 1 year ago
The key here is that the Ingress object is about routing traffic from outside the cluster to Services within the cluster. That's what option A is describing, so I'm pretty confident that's the right answer. I'll mark that one and move on to the next question.
DI
Dianne 1 year ago
Hmm, I'm a bit unsure about the difference between cost estimation and cost budgeting. I'll need to think this through carefully.
AI
Aimee 1 year ago
Hmm, I'm a bit unsure about this one. I'll need to review the concepts of backlog refinement and planning horizons to make sure I understand the right approach.
AL
Alishia 1 year ago
I remember something about BGP settings in dual WAN scenarios. Option A sounds familiar, but doesn't HSRP also play a role?
0/2000 characters

Save Cancel