Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-ACP Topic 2 Question 101 Discussion

Actual exam question for PMI's PMI-ACP exam
Question #: 101
Topic #: 2
[All PMI-ACP Questions]

Stakeholders ate displeased with the latest release o! a product's software While most stakeholders attended every sprint review they were otherwise largely uninvolved in the project What should the agile practitioner have done to ensure stakeholder satisfaction?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Amie
7 days ago
I think the agile practitioner should have communicated early and often.
upvoted 0 times
...
Clay
7 days ago
I agree with C. Stakeholders need to be actively involved, not just attend reviews. More frequent check-ins and demos would have kept them engaged.
upvoted 0 times
...
Ashlyn
21 days ago
The correct answer is C. Conducting additional stakeholder reviews and demos would have helped ensure stakeholder satisfaction. Communicating early and often is important, but not enough on its own.
upvoted 0 times
Billye
7 days ago
B) Ensured engagement among stakeholders and the product owner
upvoted 0 times
...
Valda
14 days ago
A) Communicated early and often, as outlined in the communications matrix
upvoted 0 times
...
...

Save Cancel