PMI-ACP Exam - Topic 11 Question 63 Discussion
Two similar stories A and B. are estimated at 3 story points Story C. is estimated a( 8 points Alter an iteration in which A and C were completed it is found that story A took much longer than story C.What should the agile practitioner do?
D) Reestimate all stories including values for A B and C
A) Assign story B more than 8 story points so to provide a better estimate
B) Add points to story B's iteration to account for the error but keep story B at 3 points
C) Assign more resources to story B to bring it in line with the estimate
Denny
10 months agoTamra
11 months agoJutta
11 months agoEve
11 months agoLavonda
11 months agoCharolette
11 months agoCristen
11 months agoBroderick
11 months agoTennie
11 months agoScarlet
12 months agoJessenia
12 months agoPamella
12 months agoTijuana
12 months agoFelice
12 months ago