PMI-ACP Exam - Topic 11 Question 63 Discussion
Two similar stories A and B. are estimated at 3 story points Story C. is estimated a( 8 points Alter an iteration in which A and C were completed it is found that story A took much longer than story C.What should the agile practitioner do?
D) Reestimate all stories including values for A B and C
A) Assign story B more than 8 story points so to provide a better estimate
B) Add points to story B's iteration to account for the error but keep story B at 3 points
C) Assign more resources to story B to bring it in line with the estimate
Denny
9 months agoTamra
9 months agoJutta
9 months agoEve
9 months agoLavonda
9 months agoCharolette
10 months agoCristen
10 months agoBroderick
10 months agoTennie
10 months agoScarlet
10 months agoJessenia
10 months agoPamella
10 months agoTijuana
10 months agoFelice
10 months ago