Midway through a sprint. a scrum team member advises the team of a new requirement Dial may change the initial scope What should the team do?
D) Ask the scrum master to secure additional time and resources
A) Work on requirements that (he product owner may have overlooked
B) Record the scope creep m the change management tog
C) Add the new requirement to the product backlog