You are the program manager for your organization. You're currently creating an accountability matrix starting with yourself, the program manager and the program sponsor. What program management process identifies the program sponsor?
Option B, Authorization of program processes and projects, seems like the right choice. The sponsor needs to authorize the program before it can get off the ground.