Several issues are identified on one component project in a program. During a meeting with that component's project manager, the program manager offers several suggested resolutions. Two weeks later, they meet again to review progress. The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule.
What should the program manager do?
Jeanice
2 days agoRose
3 days agoRoy
6 days agoDalene
8 days agoKyoko
26 days agoTony
11 days agoKristel
1 months agoSerina
2 months agoMaxima
2 months ago