PMI PgMP Exam - Topic 6 Question 80 Discussion
Several issues are identified on one component project in a program. During a meeting with that component's project manager, the program manager offers several suggested resolutions. Two weeks later, they meet again to review progress. The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule.What should the program manager do?
C) Emphasize that the project manager needs to address the issues and follow up at the next scheduled meeting.
A) Join project-level issue resolution meetings to accelerate the decision-making process.
B) Initiate discussions with the program governance board about assigning a more experienced project manager to the project.
D) Develop an immediate corrective action plan with the project manager and coach them on decision-making responsibilities.
Section: Volume D
Explanation
Kenneth
10 months agoRhea
10 months agoCiara
10 months agoDonte
10 months agoSunny
11 months agoOllie
11 months agoPatti
11 months agoMarica
11 months agoVinnie
11 months agoDarci
11 months agoErick
11 months agoWilda
11 months agoJosphine
11 months agoMeaghan
12 months agoSlyvia
12 months agoBenedict
12 months agoJeanice
1 year agoRose
1 year agoRoy
1 year agoVashti
1 year agoHerschel
1 year agoMariann
1 year agoDalene
1 year agoBeata
1 year agoJanna
1 year agoNgoc
1 year agoKyoko
1 year agoReena
1 year agoKenny
1 year agoTony
1 year agoKristel
1 year agoSerina
1 year agoMaxima
1 year ago