PMI PgMP Exam - Topic 6 Question 80 Discussion
Several issues are identified on one component project in a program. During a meeting with that component's project manager, the program manager offers several suggested resolutions. Two weeks later, they meet again to review progress. The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule.What should the program manager do?
C) Emphasize that the project manager needs to address the issues and follow up at the next scheduled meeting.
A) Join project-level issue resolution meetings to accelerate the decision-making process.
B) Initiate discussions with the program governance board about assigning a more experienced project manager to the project.
D) Develop an immediate corrective action plan with the project manager and coach them on decision-making responsibilities.
Section: Volume D
Explanation
Kenneth
6 months agoRhea
6 months agoCiara
7 months agoDonte
7 months agoSunny
7 months agoOllie
7 months agoPatti
8 months agoMarica
8 months agoVinnie
8 months agoDarci
8 months agoErick
8 months agoWilda
8 months agoJosphine
8 months agoMeaghan
8 months agoSlyvia
8 months agoBenedict
8 months agoJeanice
1 year agoRose
1 year agoRoy
1 year agoVashti
12 months agoHerschel
12 months agoMariann
12 months agoDalene
1 year agoBeata
12 months agoJanna
1 year agoNgoc
1 year agoKyoko
1 year agoReena
1 year agoKenny
1 year agoTony
1 year agoKristel
1 year agoSerina
1 year agoMaxima
1 year ago