Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 6 Question 69 Discussion

Actual exam question for PMI's Program Management Professional exam
Question #: 69
Topic #: 6
[All Program Management Professional Questions]

A biometrics firm has a facial recognition program with multiple components and project managers. The

project manager from the mobile device division escalates a vendor-related risk to the program manager. After assessing the risk, the program manager determines that this risk may impact other projects within the program. However, this risk has a low degree of impact and probability of occurring.

What should the program manager do first?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Sheridan
25 days ago
Ooh, I like how you're all thinking critically about this. But let's not forget the old saying - 'hope for the best, but prepare for the worst.' I think adding the risk details to the program register is a smart move, just in case it does turn into a bigger issue down the line.
upvoted 0 times
...
Malinda
26 days ago
You know, I was leaning towards option D at first. Brainstorming with the project manager could help them come up with a more tailored response. But I think Edison and Melina make a good point - communication is key, especially with a program-wide risk like this.
upvoted 0 times
...
Melina
27 days ago
I agree with Edison. Option B seems like the best move here. The program manager needs to make sure everyone is aware of this risk, even if it's not a major one. That way, they can all work together to monitor it and come up with a plan if it starts to escalate.
upvoted 0 times
...
Edison
28 days ago
Hmm, this seems like a tricky one. The risk has a low impact and probability, so I don't think we need to go all out with a contingency plan. But it's still important to communicate it to the other project managers so they can keep an eye on it.
upvoted 0 times
Roselle
7 days ago
Should we also consider a contingency plan, just in case?
upvoted 0 times
...
Virgie
8 days ago
Definitely, better to be proactive.
upvoted 0 times
...
Ronny
9 days ago
We can then monitor the situation closely.
upvoted 0 times
...
Skye
10 days ago
Agreed, transparency is key in managing risks.
upvoted 0 times
...
Janey
11 days ago
Sounds good, let's make sure everyone is aware of the risk.
upvoted 0 times
...
Leah
12 days ago
B) Communicate the risk to all project managers to manage at the component level.
upvoted 0 times
...
Pamella
13 days ago
C) Add the risk details and analysis to the program risk register.
upvoted 0 times
...
...

Save Cancel