PMI PgMP Exam - Topic 6 Question 64 Discussion

Posted by Refugia on Jan 06, 2023 at 07:56 AM

A new program component provides an opportunity to enhance program outcomes. What does the program manager use to document and monitor the opportunity?

Suggested Answer: A

Get Premium PgMP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
38 comments · newest first
OR
Oren 12 months ago
I thought the component project risk register was the way to go!
CY
Cyndy 1 year ago
The scope management plan doesn't track opportunities, right?
DO
Dorinda 1 year ago
Wait, are we sure it’s not the risk management plan?
PO
Polly 1 year ago
Agree, that makes the most sense!
MI
Micaela 1 year ago
I think it's definitely the Program risk register.
TI
Tiera 1 year ago
I’m leaning towards the component project risk register, but I’m not confident. It seems like it could be relevant for specific projects within the program.
KA
Katlyn 1 year ago
I feel like the program scope management plan is more about defining what’s included in the project, not really about documenting opportunities.
MI
Miesha 1 year ago
I remember practicing a question about risk management plans, so maybe the program risk management plan is what they’re looking for here?
MA
Marva 1 year ago
I think the program risk register might be the right choice since it helps track opportunities and threats, but I'm not entirely sure.
DO
Dominga 1 year ago
Hmm, this seems like a tricky one. I'll need to think carefully about the different probe options and where they might originate by default.
CH
Chau 1 year ago
Obligation acceleration might be the right choice here. I remember discussing how priorities can shift in those cases during class.
KI
Kimbery 1 year ago
Wait, there's a program risk register? Is that like a risk register, but with more program?
KA
Kandis 1 year ago
I don't know, this question is making my head spin. Maybe I should've studied harder instead of watching that cat video last night...
CE
Cecily 1 year ago
↳ replying to Kandis
C) Program risk management plan
FR
Franklyn 1 year ago
↳ replying to Kandis
B) Program scope management plan
ER
Erinn 1 year ago
↳ replying to Kandis
C) Program risk management plan
GA
Galen 1 year ago
↳ replying to Kandis
A) Program risk register
EL
Elsa 1 year ago
↳ replying to Kandis
B) Program scope management plan
VI
Viola 1 year ago
↳ replying to Kandis
A) Program risk register
MI
Mirta 2 years ago
Ah, tricky one! I was debating between B) Program scope management plan and C) Program risk management plan, but I guess the risk plan is the way to go.
VI
Vi 1 year ago
↳ replying to Mirta
It's always important to have a solid risk management plan in place to ensure program success.
LY
Lyda 1 year ago
↳ replying to Mirta
Yes, the Program risk management plan is specifically designed to address risks and opportunities within the program.
SH
Shawna 1 year ago
↳ replying to Mirta
I think you made the right choice, the Program risk management plan is used to document and monitor opportunities.
CH
Cherelle 2 years ago
Hmm, I was leaning towards D) Component project risk register, but I can see how the program-level risk management plan would be more appropriate here.
LE
Lelia 1 year ago
↳ replying to Cherelle
C: So true, it's all about ensuring successful outcomes for the program.
BE
Berry 1 year ago
↳ replying to Cherelle
A: Definitely, it's important to have a plan in place to manage risks effectively.
NA
Nathan 1 year ago
↳ replying to Cherelle
B: I agree, it would help document and monitor the opportunity at the program level.
ID
Idella 1 year ago
↳ replying to Cherelle
A: I think C) Program risk management plan would be the best choice.
JE
Jeanice 1 year ago
↳ replying to Cherelle
Yes, it would, but the program risk management plan is specifically designed to address risks and opportunities.
EL
Elly 1 year ago
↳ replying to Cherelle
But wouldn't the program scope management plan also play a role in this?
AL
Allene 1 year ago
↳ replying to Cherelle
I agree, it's important to document and monitor the opportunity at the program level.
LI
Lisha 1 year ago
↳ replying to Cherelle
I think C) Program risk management plan would be the best choice.
NA
Natalie 2 years ago
I think the correct answer is C) Program risk management plan. That's where you document and monitor risks, including opportunities like this new program component.
RE
Refugia 1 year ago
↳ replying to Natalie
Yes, it's important to have a plan in place to address any potential risks or opportunities that may arise.
AD
Adolph 2 years ago
↳ replying to Natalie
I agree, the program risk management plan is where we document and monitor risks, including opportunities.
BI
Billy 2 years ago
I think the Program scope management plan could also be used to document and monitor the opportunity, as it outlines the scope of the program and its components.
PH
Phung 2 years ago
I agree with Lera. The Program risk register would help in identifying and managing risks associated with the new program component.
LE
Lera 2 years ago
I think the program manager would use the Program risk register to document and monitor the opportunity.